HitchAI
Energy · President's Budget PB2027

Accelerator R&D and Production

Energy·Non-Defense (Non-050)·CJ p. 17
FY2027 Request
Parsed · CJ — verify
FY2025 enacted $27.0M
Parsed · verify

This figure was parsed from Energy's FY2027 Congressional Justification, not from a standard budget exhibit. It is approximate and it is not summable with other lines. It is published so you can check it: the citation below names the exact page it was read off. Where a dollar figure matters, verify it there before using it.

The FY2027 President's Budget requests for Accelerator R&D and Production, within Energy's Non-Defense (Non-050) account.

Funding

FY2025–FY2025

Fiscal yearBasisAmount
FY2025enacted$27.0M

Bases are separate columns and are never summed into one figure.

Authoritative context

Energy discretionary budget authority

FY2027 request$36.30B
FY2026$58.20B
Change▼ 38%

From the OMB Public Budget Database — clean, summable, and the figure to cite for an agency total. It is the whole of Energy's discretionary request, not a total of the parsed lines above, and this page never adds the two together.

Not yet extracted

What this funds

We have not extracted a program description for this line yet. That is a gap in our parsing of Energy Programs, not a statement about the program — the figures above are parsed from that document and stand on their own. The line appears on p. 17 of it.

Descriptions are backfilled agency by agency; this page picks one up automatically when it lands.

What was actually awarded

Contracts funded by this line

1 linked contract. These are obligations — lifetime awarded money — and they are not comparable to the request above and are never added to it. No total is shown: an award linked to several lines is counted in full on each, so the sum would not be a fact.

ContractVendorConfidenceObligated
W519TC25F0404
last action FY2025
BAE SYSTEMS ORDNANCE SYSTEMS INC.Medium confidence$3.0M

Confidence mix · 1 medium

Linked contracts are a floor, not a census. Coverage is bounded by how distinctively a program is named and, for performer links, to RDT&E and Procurement — O&M and military construction publish no performers. Budget figures are FY2027 request dollars; contract figures are obligations. The two measure different things and must never be summed together.

Ask Hitch

Ask this budget line

Answers come from the figures on this page and nothing else. These dollars are parsed from Energy's Congressional Justification and are approximate — confirm anything that matters against the cited page.

H
Questions this page can answer
What does Accelerator R&D and Production fund?How has the funding changed year over year?How does this sit inside Energy's discretionary budget?Where can I verify this figure?

This page carries the budget justification only. Contract obligations live at hitchintel.com/vendors; open solicitations at hitchintel.com/opportunities.