The FY2027 President's Budget requests $3.2M for Fast Flux Test Reactor Facility (WA), within Energy's Non-Defense (Non-050) account. That is up 0.0% on the FY2026 figure of $3.2M, which is the enacted appropriation.
FY2025–FY2027
| Fiscal year | Basis | Amount |
|---|---|---|
| FY2025 | enacted | $3.2M |
| FY2026 | enacted | $3.2M |
| FY2027 | request | $3.2M |
Bases are separate columns and are never summed into one figure.
Energy discretionary budget authority
From the OMB Public Budget Database — clean, summable, and the figure to cite for an agency total. It is the whole of Energy's discretionary request, not a total of the parsed lines above, and this page never adds the two together.
What this funds
Funds deactivation and decommissioning of the Fast Flux Test Facility, a sodium-cooled fast neutron test reactor at Hanford, and its support buildings, maintaining the facility in a safe condition during long-term surveillance and maintenance.
Extracted from Energy Programs, p. 17. Verbatim; nothing here is paraphrased.
Ask this budget line
Answers come from the figures on this page and nothing else. These dollars are parsed from Energy's Congressional Justification and are approximate — confirm anything that matters against the cited page.
This page carries the budget justification only. Contract obligations live at hitchintel.com/vendors; open solicitations at hitchintel.com/opportunities.