The FY2027 President's Budget requests $11.0M for Naval Petroleum Production Operations, within Energy's Non-Defense (Non-050) account. That is up 0.0% on the FY2026 figure of $11.0M, which is the enacted appropriation.
FY2025–FY2027
| Fiscal year | Basis | Amount |
|---|---|---|
| FY2025 | enacted | $11.0M |
| FY2026 | enacted | $11.0M |
| FY2027 | request | $11.0M |
Bases are separate columns and are never summed into one figure.
Energy discretionary budget authority
From the OMB Public Budget Database — clean, summable, and the figure to cite for an agency total. It is the whole of Energy's discretionary request, not a total of the parsed lines above, and this page never adds the two together.
What this funds
Funds legacy environmental cleanup and remediation at the former Naval Petroleum Reserve No. 1 (Elk Hills, California) under a corrective action agreement with the state, addressing remaining areas of contamination after the reserve's sale.
Extracted from Energy Programs, p. 17. Verbatim; nothing here is paraphrased.
Contracts funded by this line
2 linked contracts. These are obligations — lifetime awarded money — and they are not comparable to the request above and are never added to it. No total is shown: an award linked to several lines is counted in full on each, so the sum would not be a fact.
| Contract | Vendor | Confidence | Obligated |
|---|---|---|---|
| W912CH25F0391 last action FY2026 | D-2 INCORPORATED | Medium confidence | $29.2M |
| DEDT0001734 last action FY2025 | Z, INC. | Medium confidence | $1.3M |
Confidence mix · 2 medium
Linked contracts are a floor, not a census. Coverage is bounded by how distinctively a program is named and, for performer links, to RDT&E and Procurement — O&M and military construction publish no performers. Budget figures are FY2027 request dollars; contract figures are obligations. The two measure different things and must never be summed together.
Ask this budget line
Answers come from the figures on this page and nothing else. These dollars are parsed from Energy's Congressional Justification and are approximate — confirm anything that matters against the cited page.
This page carries the budget justification only. Contract obligations live at hitchintel.com/vendors; open solicitations at hitchintel.com/opportunities.