Energy·Defense (050)·CJ p. 17
FY2027 Request
$362.7M
Parsed · CJ — verify
FY2026 enacted $348.8M
Parsed · verify

This figure was parsed from Energy's FY2027 Congressional Justification, not from a standard budget exhibit. It is approximate and it is not summable with other lines. It is published so you can check it: the citation below names the exact page it was read off. Where a dollar figure matters, verify it there before using it.

The FY2027 President's Budget requests $362.7M for NNSA Sites, within Energy's Defense (050) account. That is up 4.0% on the FY2026 figure of $348.8M, which is the enacted appropriation.

Funding

FY2025–FY2027

Fiscal yearBasisAmount
FY2025enacted$368.3M
FY2026enacted$348.8M
FY2027request$362.7M

Bases are separate columns and are never summed into one figure.

Authoritative context

Energy discretionary budget authority

FY2027 request$36.30B
FY2026$58.20B
Change▼ 38%

From the OMB Public Budget Database — clean, summable, and the figure to cite for an agency total. It is the whole of Energy's discretionary request, not a total of the parsed lines above, and this page never adds the two together.

In the agency's own words

What this funds

Funds environmental cleanup at NNSA sites, chiefly Lawrence Livermore National Laboratory — including solid waste stabilization and disposition and soil and groundwater remediation at Site 300.

Extracted from Energy Programs, p. 17. Verbatim; nothing here is paraphrased.

What was actually awarded

Contracts funded by this line

136 linked contracts. These are obligations — lifetime awarded money — and they are not comparable to the request above and are never added to it. No total is shown: an award linked to several lines is counted in full on each, so the sum would not be a fact.

ContractVendorConfidenceObligated
W912PP18C0004
last action FY2023
CADDELL CONSTRUCTION CO. (DE), LLCMedium confidence$145.3M
DEBP0004604
last action FY2021
CARAHSOFT TECHNOLOGY CORPMedium confidence$95.9M
89233120FNA400255
last action FY2025
MELE ASSOCIATES INCMedium confidence$91.1M
89233125FNA000176
last action FY2026
ACCENTURE FEDERAL SERVICES LLCMedium confidence$90.3M
89233123FNA400504
last action FY2025
THUNDERCAT TECHNOLOGY, LLCMedium confidence$58.3M
DEDT0005713
last action FY2025
JOHNSON CONTROLS GOVERNMENT SYSTEMS, LLCMedium confidence$57.6M
89233124FNA400584
last action FY2024
CRITERION SYSTEMS, L.L.C.Medium confidence$57.5M
DEDT0001391
last action FY2019
METRICA TEAM VENTUREMedium confidence$53.0M

Showing 8 of 136 — most confidently matched first, largest within a confidence tier. These are not necessarily the largest 8.

Confidence mix · 136 medium

Linked contracts are a floor, not a census. Coverage is bounded by how distinctively a program is named and, for performer links, to RDT&E and Procurement — O&M and military construction publish no performers. Budget figures are FY2027 request dollars; contract figures are obligations. The two measure different things and must never be summed together.

Ask Hitch

Ask this budget line

Answers come from the figures on this page and nothing else. These dollars are parsed from Energy's Congressional Justification and are approximate — confirm anything that matters against the cited page.

H
Questions this page can answer
What does NNSA Sites fund?How has the funding changed year over year?How does this sit inside Energy's discretionary budget?Where can I verify this figure?

This page carries the budget justification only. Contract obligations live at hitchintel.com/vendors; open solicitations at hitchintel.com/opportunities.