Interior·Construction·CJ p. 105
FY2027 Request
$7.6M
Parsed · CJ — verify
FY2026 enacted $22.3M
Parsed · verify

This figure was parsed from Interior's FY2027 Congressional Justification, not from a standard budget exhibit. It is approximate and it is not summable with other lines. It is published so you can check it: the citation below names the exact page it was read off. Where a dollar figure matters, verify it there before using it.

The FY2027 President's Budget requests $7.6M for Other Program Construction, within Interior's Construction account. That is down 66% on the FY2026 figure of $22.3M, which is the enacted appropriation.

Funding

FY2026–FY2027

Fiscal yearBasisAmount
FY2026enacted$22.3M
FY2027request$7.6M

Bases are separate columns and are never summed into one figure.

Authoritative context

Interior discretionary budget authority

FY2027 request$18.80B
FY2026$17.30B
Change▲ 8.7%

From the OMB Public Budget Database — clean, summable, and the figure to cite for an agency total. It is the whole of Interior's discretionary request, not a total of the parsed lines above, and this page never adds the two together.

In the agency's own words

What this funds

IA operates telecommunication sites that are critical to the Bureaus' mission. Identifying and remediating telecommunication issues are critical to the continuity of operations. Telecommunication projects target the repair or replacement of radio towers, base stations, and infrastructure; correction of safety conditions; and damage caused by fire, acts of nature, vandalism, etc. Telecommunication projects ensure compliance with regulations, correct identified life safety deficiencies, replace systems that fall outside the narrowband requirements, and provide emergency repairs. Subactivity - Facilities/Quarters Improvement & Repair IA performs facilities/quarters improvement and repair (F/QI&R) work on existing administrative facilities. The program prioritizes projects to improve safety and protect the health of employees and the public in administrative buildings. The funds support the following: Minor Improvement and Repair: Funds are used to correct priority deficiencies and support code compliance repairs necessary to provide safe, functional facilities and minimize program personnel's exposure to potential life, safety, and health hazards. The program will focus on the disposal backlog of facilities that are ready for demolition or transfer to Tribes within the General Administration portfolio. Facility Condition Assessments: The purpose of the program is to complete a comprehensive condition assessment and inventory validation of all IA-owned or -leased real property assets on a three-year cycle. Assessments identify new deficiencies and validate existing deficiencies tracked in IA-FMS for assets that provide Trust Services to Tribes and Tribal members. Condition assessments identify DM needs and include a computation of the current replacement value of each asset, which is necessary to calculate the asset's FCI. Condition assessments include major building systems such as fire and life safety, HVAC, and electrical systems, as well as structural integrity evaluations. Emergency Repairs: The Emergency Repairs program provides reimbursement funds to mitigate or eliminate immediate threats to life, safety, health or property. Environmental Projects: The Environmental Projects program addresses environmental clean-up in accordance with environmental laws and regulations. Specifically, funds are used to assess, characterize, remediate, and monitor potential or actual releases of environmental contaminants at IA-owned general administration facilities. Environmental projects include the upgrade or replacement of storage tanks, wastewater systems, water systems, water towers, or wells; removal and disposal of contaminated soils and hazardous or toxic materials; abatement of asbestos and lead paint; and sampling and analysis of environmental contaminants, including testing for and mitigation of radon gas. Subactivity - Construction Program Management Construction Program Management provides for national strategic, operational, and liaison support for facilities programs. Staff will assist the program to ensure all major construction or renovation projects materially contribute to effective resource protection and improved overall operation of programs in the most cost effective and environmentally responsible manner possible. The program also manages and 147 Other Program Construction oversees all maintenance programs, which are accomplished through commercial contracts, Pub.L. 93- 638 contracts, Pub.L. 100-297 grants, or compacts with Tribes or Tribal organizations across the IA inventory which includes 61,024 buildings--more than 30.6 million square feet--nation-wide and includes all associated site utilities. The buildings are located in 28 States and are distributed over approximately 407 sites that are often remote and isolated. Fort Peck Water System: In accordance with the requirements of the Fort Peck Reservation Rural Water System Act of 2000, the Bureau funds operations, maintenance, and repair for the completed sections of the Fort Peck Water System located within the Fort Peck Indian Reservation boundaries. This system ensures a safe and adequate municipal, rural, and industrial water supply for the residents of the Fort Peck Indian Reservation in the State of Montana, as well as the citizens of Roosevelt, Sheridan, Daniels, and Valley counties in the State, outside the Fort Peck Indian Reservation.

Extracted from Bureau of Indian Affairs, p. 105. Verbatim; nothing here is paraphrased.

Ask Hitch

Ask this budget line

Answers come from the figures on this page and nothing else. These dollars are parsed from Interior's Congressional Justification and are approximate — confirm anything that matters against the cited page.

H
Questions this page can answer
What does Other Program Construction fund?How has the funding changed year over year?How does this sit inside Interior's discretionary budget?Where can I verify this figure?

This page carries the budget justification only. Contract obligations live at hitchintel.com/vendors; open solicitations at hitchintel.com/opportunities.