## Summary

This activity requests $106.9M in FY2027, 100% of project 675056, down 30% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

## What the FY2027 request buys

**FY2027 planned work.** Will continue Agile and incremental software code development for version 1.0; continue development flight testing; create, test, and deploy software fix releases to integration labs and development flight test aircraft; prepare for Initial Operational Test and Evaluation (IOT&E).

**FY2026 to FY2027 change.** Funding levels decrease because test aircraft modification work will be complete; FY 2027 focus will be delivering software version 1.0 to flight test and fixing discrepancy reports found during development flight test.

## Before the request year

**FY2026 plans — current year.** Will continue Agile and incremental software code development for version 1.0; continue hardware/software integration Software Integration Lab tests; complete desktop training tool development; complete and deliver second test aircraft; complete ground test and flight testing on software version 0.5; start development flight test efforts on software version 1.0 (AFGSC-approved minimum viable product).

## Funding

| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 200.0 |
| FY2026 | Enacted | 153.1 |
| FY2027 | Request | 106.9 |

> Prior, current and budget year only — an R-2A activity carries no five-year plan. It sums exactly into its project in the request year and not necessarily in any other.

## Source & machine access

- **Source:** FY2027 Department of the Air Force RDT&E Budget Justification, Exhibit R-2A, PE 0101113F project 675056 (PB PB2027). Narrative is the government's own text.
- **No marks, no contractors at this grain** — congressional marks land on the program element and R-3 performers on the project.
- **MCP:** `mcp.hitchintel.com` — `budget_get_activity`.

*HitchAI is an independent intelligence service, not affiliated with the U.S. Department of Defense. Budget figures are requests/estimates, not obligations.*