# Automatic Ground Collision Avoidance System (AGCAS) E/F/G

**R-2A activity** of project 1662 — F/A-18 Improvement  
**Program element:** 0204136N — F/A-18 Squadrons  
**Component:** U.S. Navy · **Budget Activity:** 7  
**Vintage:** President's Budget PB2027  
**Canonical URL:** https://hitchintel.com/programs/0204136N/1662/a1  
**Parent:** https://hitchintel.com/programs/0204136N/1662

## Summary

This activity requests $36.1M in FY2027, 14% of project 1662, up 101% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

## What the FY2027 request buys

**FY2027 planned work.** Develop, test, and evaluate software changes required for the development of AGCAS for F/A-18E/F and EA-18G variants. Research changes needed to the Mission Computer (MC), Flight Control Computer (FCC), and Digital Video Map Computer (DVMC) for all blocks of F/A-18 E/F and EA-18G aircraft.

**FY2026 to FY2027 change.** FY2026 to FY2027 increase of $18.148M is due to the ramp up of developing, testing and evaluating software for AGCAS on F/A-18 E/F and EA-18G aircraft. Evaluation includes changes required for the MC, FCC, and DVMC-U on all blocks of F/A-18E/F and EA-18G. The F/A-18 and EA-18G communities have experienced several aircrew fatalities and loss of aircraft due to Controlled Flight into Terrain (CFIT). To mitigate this risk, AGCAS has been identified as a critical safety enhancement that will execute automatic, last-instant ground-collision avoidance maneuvers. This is a required capability to reduce the risk of CFIT, thus enhancing aircrew survivability, and improving overall safety.

## Before the request year

**FY2026 plans — current year.** Conduct evaluation of software changes required for the development of AGCAS for F/A-18E/F and EA-18G variants. Research changes needed to the Mission Computer (MC), Flight Control Computer (FCC), and Digital Video Map Computer (DVMC) for all blocks of F/A-18 E/F and EA-18G aircraft.

## Funding

| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 1.7 |
| FY2026 | Enacted | 18.0 |
| FY2027 | Request | 36.1 |

> Prior, current and budget year only — an R-2A activity carries no five-year plan. It sums exactly into its project in the request year and not necessarily in any other.

## Other activities in project 1662

- [Advanced Electronic Warfare (ADVEW)](https://hitchintel.com/programs/0204136N/1662/a0) — FY2027 63.3
- [Multi-System Integration (MSI)](https://hitchintel.com/programs/0204136N/1662/a7) — FY2027 59.2
- [F/A-18 Beyond Line Of Sight (BLOS) Comms](https://hitchintel.com/programs/0204136N/1662/a2) — FY2027 33.4
- [Digital Video Map Computer-Upgrade (DVMC-U)](https://hitchintel.com/programs/0204136N/1662/a4) — FY2027 14.7
- [Next Generation Naval Mission Planning System (NGNMPS)](https://hitchintel.com/programs/0204136N/1662/a9) — FY2027 11.8
- Brizo Beacon — FY2027 10.2
- F/A-18 Obsolescence Redesign — FY2027 9.5
- Flight Plan Engineering / System Configuration Set Development and Integration — FY2027 9.1
- USMC Capability Upgrades — FY2027 6.1
- F/A-18 E/F/G Network Cyber Defense — FY2027 5.0
- Live Virtual Constructive (LVC) Aircraft Integration — FY2027 0.0

## Source & machine access

- **Source:** FY2027 Department of the Navy RDT&E Budget Justification, Exhibit R-2A, PE 0204136N project 1662 (PB PB2027). Narrative is the government's own text.
- **No marks, no contractors at this grain** — congressional marks land on the program element and R-3 performers on the project.
- **MCP:** `mcp.hitchintel.com` — `budget_get_activity`.

*HitchAI is an independent intelligence service, not affiliated with the U.S. Department of Defense. Budget figures are requests/estimates, not obligations.*