RDT&E Project · President's Budget PB2027

Extended Range GMLRS

FY2027 Request
$19.5M
▼ 37% vs FY2026
HitchAI read

Project DL1 — Extended Range GMLRS requests $19.5M in FY2027, 27% of the $73.6M requested for program element 0205778A, down 37% on FY2026. 3 R-2A activities decompose the request, 1 new this cycle.

MarketGuided Missiles (mfg)

Matched on this project's title. A title match, not a curated taxonomy — narrative-only matches are not shown at all rather than shown with a caveat nobody reads. No market size is quoted here: a market spans appropriations far beyond this program element.

FY2027 Request
$19.5M
▼ 37% vs FY2026
FY2026 Enacted
$30.8M
In law
Project detail

What project DL1 buys

The DL1 project code funds efforts to enhance Extended Range Guided Multiple Launch Rocket System (ER-GMLRS) rockets and common components. The Army is requesting funding for ER-GMLRS Research, Development, Test and Evaluation (RDT&E) development, integration, and test activities to enhance operational capabilities including increased range, improved lethality and survivability, enhanced flight performance, and Assured Positioning, Navigation and Timing (APNT). FY 2027 funding initiates ER-GMLRS EAW software development and system integration efforts to procure test articles to support system level development and qualification.

R-3 lines of work
  • Management Services
  • Product Development
  • Test and Evaluation
Funding trajectory

Project DL1 funding, FY2026–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

25030.8FY26ENACTED19.5FY27REQUEST19.1FY2814.1FY2913.9FY3014.0FY31
Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2026Enacted30.8
FY2027Request19.5
FY2028Outyear19.1
FY2029Outyear14.1
FY2030Outyear13.9
FY2031Outyear14.0
Inside the project

3 accomplishments / planned programs

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Coverage is partial across the corpus, so count activities, never total them.

ER-GMLRS Enhanced Alternative Warhead QualificationNEW
FY2025 actual
FY2026 enacted
FY2027 request$19.5M

FY2027 planned work Initiate procurement of test articles and software development to support integration and testing requirements of the EAW capability into ER-GMLRS munition. Conduct initial baseline review and system requirement review.

FY2026 to FY2027 change Funding increase due to the initiation of EAW integration into ER-GMLRS in FY 2027.

ER-GMLRS Development & Qualification (redesign SMPS)▼ 100%
FY2025 actual
FY2026 enacted$9.1M
FY2027 request

FY2026 to FY2027 change Funding decrease due to completion of the ER-GMLRS SMPS redesign qualification in FY 2026.

FY2026 plans — current year Complete system level qualification of the ER-GMLRS with redesigned SMPS.

Enhanced Alternative Warhead Qualification▼ 100%
FY2025 actual
FY2026 enacted$21.7M
FY2027 request

FY2026 to FY2027 change Funding decrease due to completion of the qualification of the EAW modification on the standard range GMLRS rocket in FY 2026.

FY2026 plans — current year Complete system qualification, including launcher and rocket operational flight software development, for GMLRS as a necessary step prior to integration of EAW into ER-GMLRS.