# Exploitation Applications

**R-2A activity** of project 670001 — Air Force TENCAP  
**Program element:** 0207247F — Air Force TENCAP  
**Component:** U.S. Air Force · **Budget Activity:** 7  
**Vintage:** President's Budget PB2027  
**Canonical URL:** https://hitchintel.com/programs/0207247F/670001/a0  
**Parent:** https://hitchintel.com/programs/0207247F

## Summary

This activity requests $31.2M in FY2027, 61% of project 670001, up 21% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

## What the FY2027 request buys

**FY2027 planned work.** - Will continue to rapidly prototype projects and focus warfighter support and resource allocation based on AF TENCAP mission/investment areas - Will continue to rapidly prototype projects and focus warfighter support and resource allocation based on AF TENCAP's focused efforts to increase Battlespace Awareness and Command and Control; support to Special Operations Forces and Advanced Capabilities; support to Space; and support to ISR and Combat Applications to meet Air Force and Joint Warfighter requirements

**FY2026 to FY2027 change.** Funding increased to fund additional rapid prototype projects and focus warfighter support and resource allocation based on AF TENCAP mission/investment areas

## Before the request year

**FY2026 plans — current year.** - Continues to rapidly prototype projects and focus warfighter support and resource allocation based on AF TENCAP mission/investment areas - Continues to rapidly prototype projects and focus warfighter support and resource allocation based on AF TENCAP's focused efforts to increase Battlespace Awareness and Command and Control; support to Special Operations Forces and Advanced Capabilities; support to Space; and support to ISR and Combat Applications to meet Air Force and Joint Warfighter requirements

## Funding

| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 24.1 |
| FY2026 | Enacted | 25.8 |
| FY2027 | Request | 31.2 |

> Prior, current and budget year only — an R-2A activity carries no five-year plan. It sums exactly into its project in the request year and not necessarily in any other.

## Other activities in project 670001

- [Moving Target Engagement](https://hitchintel.com/programs/0207247F/670001/a1) — FY2027 19.7

## Source & machine access

- **Source:** FY2027 Department of the Air Force RDT&E Budget Justification, Exhibit R-2A, PE 0207247F project 670001 (PB PB2027). Narrative is the government's own text.
- **No marks, no contractors at this grain** — congressional marks land on the program element and R-3 performers on the project.
- **MCP:** `mcp.hitchintel.com` — `budget_get_activity`.

*HitchAI is an independent intelligence service, not affiliated with the U.S. Department of Defense. Budget figures are requests/estimates, not obligations.*