R-2A Activity · President's Budget PB2027

Flight Test

FY2027 Request
$170.1M
◆ Restart — nothing in FY2026
HitchAI read

This activity requests $170.1M in FY2027, 17% of project MT04 — a restart, funded in FY2025 and zeroed in FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

Restart

This activity was funded in FY2025 ($31.9M), zeroed in FY2026, and requests $170.1M again in FY2027. A restart has an incumbent and a new start does not; with a zero current year there is no percentage to quote, which is why it appears in no growth ranking.

FY2027 Request
$170.1M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$31.9M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project MT04 of PE 0603914C. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

- Increase is due to transfers from Aegis BMD Test (0604878C), BMD Sensor Test (0604879C), and BMD Midcourse Defense Segment Test (0604887C) Program Elements (PEs) to the BMD Test PE (0603914C).

FY2026 to FY2027 change

- Increase from FY 2026 to FY 2027 due to transfers from Aegis BMD Test (0604878C), BMD Sensor Test (0604879C), and BMD Midcourse Defense Segment Test (0604887C) Program Elements (PEs) to the BMD Test PE (0603914C). This strategy better positions the Agency to execute the President's Executive Orders 14186 to develop Missile Defense System-Next capabilities to defend the United States from the most catastrophic threat.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

- No funding is requested in FY 2026 based on the current IMTP requirements.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

50100150031.9FY25ACTUAL0.0FY26ENACTED170.1FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual31.9
FY2026Enacted0.0
FY2027Request170.1

This activity is 17% of project MT04's FY2027 request and 16% of PE 0603914C's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

6 activities in project MT04

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Test Infrastructure$331.4M ▲ 62%
Missile Defense System - Next: PT Upgrade/Recap, PC Recap$329.0M NEW
Flight Test — this activity$170.1M RESTART
Program Planning and Operations$91.3M ▼ 14%
Ground Test$74.3M ▼ 17%
Engineering and Test Analysis$27.4M ▲ 10%
Source
FY2027 Office of the Secretary of Defense RDT&E Budget Justification · Exhibit R-2A · PE 0603914C, project MT04 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0603914C/MT04/a1.md · MCP mcp.hitchintel.combudget_get_activity