What the FY2027 request buys
Verbatim from the R-2A exhibit for project 2234 of PE 0604610N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.
-Continue APB 6 (INC 2) software development and Engineering Testing. -Continue APB 6 (Hammerhead) software development and testing in support of field early operational capability (EOC). -Continue platform integration of APB 6 (INC 2) with launch platforms (P-8A, MH-60R, CRUDES). -Continue addressing emergent and stop gap capability needs (TDHK).
The overall increase of $7.293 million from FY 2026 to FY 2027, due to reduced FY2026 funding from Reconciliation Incongruence adjustment
FY2026: the year under way
Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.
-Continue APB 6 (INC 2) software development and Engineering Testing. -Complete APB 6 (Hammerhead) software development and field early operational capability (EOC) -Continue platform integration of APB 6 (INC 2) with launch platforms (P-8A, MH-60R, CRUDES). -Continue addressing emergent and stop gap capability needs.
Three years, and no five-year plan
An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 13.4 |
| FY2026 | Enacted | 5.1 |
| FY2027 | Request | 12.4 |
This activity is 100% of project 2234's FY2027 request and 12% of PE 0604610N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.
1 activity in project 2234
Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.