This activity requests $13.5M in FY2027, 61% of project EZ8, down 55% on FY2026. The R-2A exhibit describes it across FY2025–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$13.5M
▼ 55% vs FY2026
FY2026 Enacted
$30.3M
▲ 4.4% vs FY2025
FY2025 Actual
$29.0M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project EZ8 of PE 0604622A. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

FY 2027 Base Plan provides funding to award remaining Phase 3 contract milestones completing the prototype effort in support of First Unit Issued (FUI). Activities funded include Developmental Testing of M-Code hardware and software, technical support, transportation and reversion of test assets, and program support.

FY2026 to FY2027 change

Decrease in FY 2027 due to completion of MTA-RP and development effort.

Before the request year

FY2025–FY2026: what came before

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

FY 2026 Base Plan funds Phase 3 vendor award - Build Prototypes for First Unit Issued (FUI). Activities funded include acquisition and integration of M-Code hardware and software, technical support, operational testing and evaluation, cyber security tests and scans, and program support.

FY2025 accomplishments

FY 2025 funds the completion of Phase 1 - Competitive Demonstration and Evaluation of up to three vendor solutions, awards 2 selected vendors Phase 2 - Vendor Prototype Build, and organizations to test/evaluate and provide support during the developmental test & evaluation. Activities funded include program management, technical design reviews, test, cyber, prototypes, contractor support and spares to support test, and Government support to vendors using government-provided software.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25029.0FY25ACTUAL30.3FY26ENACTED13.5FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual29.0
FY2026Enacted30.3
FY2027Request13.5

This activity is 61% of project EZ8's FY2027 request and 31% of PE 0604622A's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

2 activities in project EZ8

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Tactical Wheeled Vehicle Leader Follower (Autonomous Transport Vehicle-System) — this activity$13.5M ▼ 55%
Tactical Wheeled Vehicle Leader Follower (Autonomous Transport Vehicle-System) Follow-on Pathway$8.7M NEW
Source
FY2027 Department of the Army RDT&E Budget Justification · Exhibit R-2A · PE 0604622A, project EZ8 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.