R-2A Activity · President's Budget PB2027

C-UAS System Development and Integration

FY2027 Request
$13.6M
▲ 192% vs FY2026
HitchAI read

This activity requests $13.6M in FY2027, 100% of project 3241, up 192% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$13.6M
▲ 192% vs FY2026
FY2026 Enacted
$4.7M
▲ 187% vs FY2025
FY2025 Actual
$1.6M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 3241 of PE 0604636N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Navy Shore C-UxS systems need to continue to evolve due to the rapidly evolving UAS capability, to reduce operator burden, and to increase interoperability of fixed facility Navy sites with joint C-UxS systems and with C-UxS systems on Navy ships.

FY2026 to FY2027 change

The program reflects a increase from FY26 to FY27 due to the support for testing of material solutions and the integration of networking capabilities essential for system evaluation and performance validation.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

Continues to provide funding for refinement of material solutions, threat assessments, identification and development of advanced target discrimination, defeat (kinetic and non-kinetic) capabilities, and integration into the C-sUAS FoS. Provide management and technical support for the C-sUAS System Under Test (SUT). Initiate system assessment. In partnership with the Joint C-sUAS Office (JCO), identify or develop additional detect and deter capabilities to integrate into the C-sUAS FoS. As the JCO designated CORIAN Acquisition Lead, continue development, implementation and integration of additional sensor modalities to improve system detect/ID/track/defeat capabilities. Continue efforts to improve interoperability between ashore and afloat C-sUAS systems. Funding provides for continued development of data fusion architecture for external sensor integration into a C-sUAS common Command and Control (C2). Provide systems engineering support for the technology development and acquisition strategy for fielding material solutions.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

01.6FY25ACTUAL4.7FY26ENACTED13.6FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual1.6
FY2026Enacted4.7
FY2027Request13.6

This activity is 100% of project 3241's FY2027 request and 65% of PE 0604636N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

1 activity in project 3241

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

C-UAS System Development and Integration — this activity$13.6M ▲ 192%
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0604636N, project 3241 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.