# Joint Transportation Management System Acquisition/Development

**R-2A activity** of project 646682 — JTMS DEVELOPMENT  
**Program element:** 0604668F — JTMS Development  
**Component:** U.S. Air Force · **Budget Activity:** 4  
**Vintage:** President's Budget PB2027  
**Canonical URL:** https://hitchintel.com/programs/0604668F/646682/a0  
**Parent:** https://hitchintel.com/programs/0604668F

## Summary

This activity requests $57.8M in FY2027, 100% of project 646682, down 54% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

## What the FY2027 request buys

**FY2027 planned work.** 1) Continue Organizational Change Management and communications. 2) Continue Analysis-Level Business Process Reengineering across Strategic Sealift, Strategic Airlift, and OCONUS freight lines of business. 3) Consolidate JTMS Support Activities (Program Management, Engineering, Functional Support (finance and logistics), and Auditability). 4) Continue to procure software to configure material solution and procure software required to support material solution fielding. 5) Continue standup and securing of the JTMS materiel solution cloud hosting environment and components hosted within. 6) Continue Design-Level Business Process Reengineering and Materiel Solution Blueprinting across CONUS freight line of business. 7) Configuration of materiel solution to support lines of operation under CONUS freight. 8) Begin limited deployment of integrated transportation and financial management capabilities. 9) Developmental and Operational Testing activities. 10) Develop training approach, mechanisms, and environments.

**FY2026 to FY2027 change.** Funding in FY2027 was reduced by $66.985 million for Advisory and Assistance Services to promote efficiencies and advance the policies of the Administration in alignment with Executive Order 14222.

## Before the request year

**FY2026 plans — current year.** 1) Continue Organizational Change Management and communications. 2) Consolidate JTMS Support Activities (Program Management, Engineering, Functional Support (finance and logistics), and Auditability). 3) Continue standup and securing of the JTMS materiel solution cloud hosting environment and components hosted within. 4) Continue Design-Level Business Process Reengineering and Materiel Solution Blueprinting across CONUS freight line of business. 5) Procure necessary software to configure material solution. 6) Configuration of materiel solution to support lines of operation under CONUS freight. 7) Begin limited deployment of integrated transportation and financial management capabilities. 8) Developmental and Operational Testing activities. 9) Develop training approach, mechanisms, and environments.

## Funding

| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 71.6 |
| FY2026 | Enacted | 124.8 |
| FY2027 | Request | 57.8 |

> Prior, current and budget year only — an R-2A activity carries no five-year plan. It sums exactly into its project in the request year and not necessarily in any other.

## Source & machine access

- **Source:** FY2027 Department of the Air Force RDT&E Budget Justification, Exhibit R-2A, PE 0604668F project 646682 (PB PB2027). Narrative is the government's own text.
- **No marks, no contractors at this grain** — congressional marks land on the program element and R-3 performers on the project.
- **MCP:** `mcp.hitchintel.com` — `budget_get_activity`.

*HitchAI is an independent intelligence service, not affiliated with the U.S. Department of Defense. Budget figures are requests/estimates, not obligations.*