RDT&E Project · President's Budget PB2027

DevSecOps

Project 673509·PE 0604840F — F-35 C2D2·U.S. Air Force·BA7
FY2027 Request
$19.7M
▼ 1.1% vs FY2026
HitchAI read

Project 673509 — DevSecOps requests $19.7M in FY2027, 1.7% of the $1.13B requested for program element 0604840F, down 1.1% on FY2026. 1 R-2A activity decomposes the request. August Schell Enterprises is the largest named R-3 performer at $5.8M, 30% of the project's FY2027 R-3 total.

MarketsCustom Software / ProgrammingCyber, C2 & Networks (programs)

Matched on this project's title. A title match, not a curated taxonomy — narrative-only matches are not shown at all rather than shown with a caveat nobody reads. No market size is quoted here: a market spans appropriations far beyond this program element.

FY2027 Request
$19.7M
▼ 1.1% vs FY2026
FY2026 Enacted
$19.9M
▲ 52% vs FY2025
FY2025 Actual
$13.0M
Prior year
Project detail

What project 673509 buys

The F-35 Software Development, Security & Operations (DevSecOps) Cloud platform environment allows for US Government and contracted software development teams to produce, test and deploy capabilities for F-35 supported Project Management Offices (PMO) and Directorates. This includes providing support to the Combat Data Systems (CDS), Air Vehicle (AV), Maintenance Systems (MxSYS), Propulsion, Training Systems and Simulation (TSS) PMOs, and Directorate of Engineering. The mission of DevSecOps is to provide a centralized F-35 Data repository, a consolidated F-35 software development environment, and support for system development lifecycle (SDLC) of the F-35 platform, allowing for rapid release cycles to keep the F-35 ahead of its adversaries. Investment in, and modernization of, DevSecOps include efforts to support F-35 Software modernization efforts, develop organic government software capabilities, support SDLC and flight-testing capabilities, enhance the security posture of the software development pipeline, and support goals of reducing long-term on-premises infrastructure environments cost, ultimately resulting in reducing fleet delivery timelines. This program element included all necessary expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program elements 0605829F, 0605831F, 0605833F, and 0605898F. Funding allocations at the project level have historically been subject to change due to the complexity of the F-35 budget structure and cost share ratios. The program will ensure any within-PE adjustments during execution year are reflected in future budget submissions.

R-3 lines of work
  • Support
Funding trajectory

Project 673509 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

013.0FY25ACTUAL19.9FY26ENACTED19.7FY27REQUEST4.6FY284.7FY294.8FY304.9FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual13.0
FY2026Enacted19.9
FY2027Request19.7
FY2028Outyear4.6
FY2029Outyear4.7
FY2030Outyear4.8
FY2031Outyear4.9
Inside the project

1 accomplishment / planned program

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Each describes FY2027 work in enough detail to have its own page; the rest are shown here in full. Coverage is partial across the corpus, so count activities, never total them.

FY2025 actual$13.0M
FY2026 enacted$19.9M
FY2027 request$19.7M

Continue development and support for DevSecOps infrastructure, platform, software development pipeline, and joint F-35 organizational connections. Continue to revise the transition plan based on emerging requirements to support stand-up of a team consisting of Industry and Government software development in support of software…

Read the FY2027 plan →
Who's building it

Named performers on project 673509

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

August Schell Enterprises
$5.8M · 30%
Amazon Web Services
$3.3M · 17%