R-2A Activity · President's Budget PB2027

USN Unique

FY2027 Request
$12.4M
▼ 9.2% vs FY2026
HitchAI read

This activity requests $12.4M in FY2027, 100% of project 2562, down 9.2% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$12.4M
▼ 9.2% vs FY2026
FY2026 Enacted
$13.7M
▼ 3.6% vs FY2025
FY2025 Actual
$14.2M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 2562 of PE 0604840N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Efforts include USN Unique Operational Testing, supporting various integrated tests and investigations. Major testing event include but are not limited to TOPGUN Support, Orange Flag, JSOW LAR Investigation, Patriot Support, Hornet H16 Interoperability, Fleet Anomaly Investigations, Interoperability Large Force Exercise, and other emerging USN test priorities. The following will be funded in order to support various tests and investigations: manpower, weapons, flight hours, range time, and chase, target & tanker support assets, as well as USN systems engineering efforts and other emerging USN requirements.

FY2026 to FY2027 change

Decrease from FY2026 to FY2027 is due to decrease in test support required at Naval Air Forces Pacific.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

Efforts include USN Unique Operational Testing, supporting various integrated tests and investigations. Major testing event include but are not limited to TOPGUN Support, Orange Flag, JSOW LAR Investigation, Patriot Support, Hornet H16 Interoperability, Fleet Anomaly Investigations, Interoperability Large Force Exercise, and other emerging USN test priorities. The following will be funded in order to support various tests and investigations: manpower, weapons, flight hours, range time, and chase, target & tanker support assets, as well as USN systems engineering efforts and other emerging USN requirements.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

014.2FY25ACTUAL13.7FY26ENACTED12.4FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual14.2
FY2026Enacted13.7
FY2027Request12.4

This activity is 100% of project 2562's FY2027 request and 2.9% of PE 0604840N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

1 activity in project 2562

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

USN Unique — this activity$12.4M ▼ 9%
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0604840N, project 2562 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0604840N/2562/a0.md · MCP mcp.hitchintel.combudget_get_activity