R-2A Activity · President's Budget PB2027

Facilities and Infrastructure Costs

Activity a1·Project MST-01 — MISSION SUPPORT·PE 0605001E·Defense-Wide
FY2027 Request
$28.6M
▼ 11% vs FY2026
HitchAI read

This activity requests $28.6M in FY2027, 26% of project MST-01, down 11% on FY2026. The R-2A exhibit describes it across FY2025–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$28.6M
▼ 11% vs FY2026
FY2026 Enacted
$32.3M
▲ 14% vs FY2025
FY2025 Actual
$28.4M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project MST-01 of PE 0605001E. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

- Continue to fund building rent, General Services Administration lease overhead costs, building maintenance and repairs, building utilities and cleaning services; Pentagon Force Protection Agency security guards; Defense Information Systems Agency telecommunication service; printing and reproduction.

FY2026 to FY2027 change

The FY 2027 decrease reflects a reduction in planned facilities projects.

Before the request year

FY2025–FY2026: what came before

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

- Continue to fund building rent, General Services Administration lease overhead costs, building maintenance and repairs, building utilities and cleaning services; Pentagon Force Protection Agency security guards; Defense Information Systems Agency telecommunication service; printing and reproduction.

FY2025 accomplishments

- Continue to fund building rent, General Services Administration lease overhead costs, building maintenance and repairs, building utilities and cleaning services; Pentagon Force Protection Agency security guards; Defense Information Systems Agency telecommunication service; printing and reproduction.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25028.4FY25ACTUAL32.3FY26ENACTED28.6FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual28.4
FY2026Enacted32.3
FY2027Request28.6

This activity is 26% of project MST-01's FY2027 request and 26% of PE 0605001E's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

4 activities in project MST-01

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the program-element page.

Mission Support Civilian Personnel Salaries$76.4M ▼ 4%
Facilities and Infrastructure Costs — this activity$28.6M ▼ 11%
Mission Support Travel$3.1M ▼ 20%
Accounting and Audit
Source
FY2027 Office of the Secretary of Defense RDT&E Budget Justification · Exhibit R-2A · PE 0605001E, project MST-01 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access