RDT&E Project · President's Budget PB2027

AN/TPY-2 Sensor

FY2027 Request
$132.1M
◆ New start in FY2027
HitchAI read

Project B1H — AN/TPY-2 Sensor requests $132.1M in FY2027, 13% of the $1.05B requested for program element 0605058A — a new start, with no prior-year and no current-year money. 2 R-2A activities decompose the request, 2 new this cycle. RTX / Raytheon is the largest named R-3 performer at $127.6M, 97% of the project's FY2027 R-3 total.

New start

This project requests $132.1M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

MarketsAir & Missile DefenseElectronics & Precision Equipment Repair

Matched on this project's title. A title match, not a curated taxonomy — narrative-only matches are not shown at all rather than shown with a caveat nobody reads. No market size is quoted here: a market spans appropriations far beyond this program element.

FY2027 Request
$132.1M
President's Budget
Project detail

What project B1H buys

Army Navy/Transportable Radar Surveillance and Control-2 (AN/TPY-2) radar contributes to regional defense by developing, delivering, and deploying/redeploying AN/TPY-2 radars for operations or tests.

R-3 lines of work
  • Product Development
  • Support
Funding trajectory

Project B1H funding, FY2027–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

501001502000132.1FY27REQUEST62.2FY28173.9FY2981.2FY30203.8FY31
Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2027Request132.1
FY2028Outyear62.2
FY2029Outyear173.9
FY2030Outyear81.2
FY2031Outyear203.8
Inside the project

2 accomplishments / planned programs

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. 1 of them describes FY2027 work in enough detail to have its own page; the rest are shown here in full. Coverage is partial across the corpus, so count activities, never total them.

FY2025 actual
FY2026 enacted
FY2027 request$127.6M

- Continue development and testing of a Test Antenna Equipment Unit (AEU) to support integration of THAAD into the Army's Integrated Battle Command System (IBCS) architecture and support other THAAD testing requirements. - Conduct planning and testing the cybersecurity controls, maintains RMF authorizations for managed information…

Read the FY2027 plan →
Program OperationsNEW
FY2025 actual
FY2026 enacted
FY2027 request$4.6M

FY2027 planned work - Provide technical and business management support activities to provide critical program status and decision quality data. - Ensure compliance with internal and external direction, policies, and regulations to deliver critical capability within a consistent and disciplined process. - Conduct internal program reviews to measure program progress. - Continue a Mission Assurance and Manufacturing Engineering Program to include Quality, Configuration Management, Manufacturing, Engineering, and Safety in all phases of the system life cycle, throughout the supply chain, and at all levels of assembly emphasizing high yield rates which minimize test and rework costs. - Provide Quality Safety and…

FY2026 to FY2027 change The increase from FY 2026 to FY 2027 is the result of the transfer of efforts from the Missile Defense Agency to the Army.

Who's building it

Named performers on project B1H

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

RTX / Raytheon
$127.6M · 97%
STRATEGIC ALLIANCE SOLUTIONS
$0.9M · 0.7%