R-2A Activity · President's Budget PB2027

Capability Development/Modernization

FY2027 Request
$848.6M
◆ New start in FY2027
HitchAI read

This activity requests $848.6M in FY2027, 92% of project B1K — a new start with no prior-year and no current-year money. The R-2A exhibit describes it across FY2027, including what the FY2027 money is planned to buy.

New start

This activity requests $848.6M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

FY2027 Request
$848.6M
President's Budget
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project B1K of PE 0605058A. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

- Accelerates iterative development and incremental release of weapon system enhancements planned for THAAD 27.1 and Future System Builds. - Accelerates delivery of critical capabilities to increase the THAAD Weapon System's threat space resulting in greater effectivity against advanced ballistic/non-ballistic threats. - Accelerates iterative development of IBCS THAAD Integration to execute and deliver in accordance with program defined milestones and objectives. - Provides upgrades and modernization efforts to THAAD development labs in order to support current and future THAAD weapon system development.

FY2026 to FY2027 change

The increase from FY 2026 to FY 2027 is the result of the transfer of efforts from the Missile Defense Agency to the Army.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

2505007500848.6FY27REQUEST
Request
Fiscal YearEstimate TypeAmount ($M)
FY2027Request848.6

This activity is 92% of project B1K's FY2027 request and 81% of PE 0605058A's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

4 activities in project B1K

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Capability Development/Modernization — this activity$848.6M NEW
THAAD Test$31.2M NEWProgram Operations$24.7M NEW
Details are provided under separate cover$17.3M NEW
Source
FY2027 Department of the Army RDT&E Budget Justification · Exhibit R-2A · PE 0605058A, project B1K (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.