R-2A Activity · President's Budget PB2027

Long Range Precision Munition

FY2027 Request
$30.5M
▲ 32% vs FY2026
HitchAI read

This activity requests $30.5M in FY2027, 100% of project A56, up 32% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$30.5M
▲ 32% vs FY2026
FY2026 Enacted
$23.2M
In law
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project A56 of PE 0605345A. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Continue the system environmental and safety qualification and airworthiness test program and conduct a ground operational demonstration for LRPM. Continue LRPM integration of maturing LE technologies, technical valuations, program transition preparation, and planning, preparation, and initiation of additional capabilities development to increase the LE Family of Systems lethality by providing the capability to strike and destroy, disrupt, or neutralize time sensitive or fleeting targets through increased cruise speed and to reduce the LRPM susceptibility to threat countermeasures optimized to defeat slow moving loitering munitions. Initiate the planning and preparation for the development of additional capabilities.

FY2026 to FY2027 change

This effort was realigned from PE 0609345A/ Project A46 Long Range Precision Munition (LRPM) beginning FY 2027 and continues work previously performed under that PE.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

Initiate the system environmental and safety qualification and airworthiness test program for LRPM. Continue LRPM integration of maturing LE technologies, technical evaluations and program transition planning.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25023.2FY26ENACTED30.5FY27REQUEST
Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2026Enacted23.2
FY2027Request30.5

This activity is 100% of project A56's FY2027 request and 3.7% of PE 0605345A's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

1 activity in project A56

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Long Range Precision Munition — this activity$30.5M ▲ 32%
Source
FY2027 Department of the Army RDT&E Budget Justification · Exhibit R-2A · PE 0605345A, project A56 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0605345A/A56/a0.md · MCP mcp.hitchintel.combudget_get_activity