# Test and Evaluation

**R-2A activity** of project 1110 — Precision Attack Strike Munition (PASM)  
**Program element:** 0605450M — Joint Air-to-ground Missile (JAGM)  
**Component:** U.S. Navy · **Budget Activity:** 5  
**Vintage:** President's Budget PB2027  
**Canonical URL:** https://hitchintel.com/programs/0605450M/1110/a1  
**Parent:** https://hitchintel.com/programs/0605450M/1110

## Summary

This activity requests $17.4M in FY2027, 9.2% of project 1110, up 32% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

## What the FY2027 request buys

**FY2027 planned work.** FY 2027 Funding will support required Developmental Test and Evaluation (DT&E), Integrated Test and Evaluation (IT&E) and Operational Test and Evaluation (OT&E) to support Early Operational capability. This includes all container qualification, qualification and airworthiness testing for the PASM and modified launcher, continued warhead qualification efforts and a Quick Reaction Assessment of the PASM capability. Delta qualification and airworthiness testing to complete the full qualification of PASM on AH-1Z will begin.

**FY2026 to FY2027 change.** Funding increase from FY 2026 to FY2027 is due to increased Test and Evaluation costs to achieve EOC.

## Before the request year

**FY2026 plans — current year.** FY 2026 funding will support Modeling and Simulation (M&S) and initial Developmental Test and Evaluation (DT&E), to include but not limited to component level testing, ground and captive carry flight testing.

## Funding

| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 1.5 |
| FY2026 | Enacted | 13.2 |
| FY2027 | Request | 17.4 |

> Prior, current and budget year only — an R-2A activity carries no five-year plan. It sums exactly into its project in the request year and not necessarily in any other.

## Other activities in project 1110

- [Product Development](https://hitchintel.com/programs/0605450M/1110/a0) — FY2027 117.5
- [Modular Common Launcher (MCL) Development](https://hitchintel.com/programs/0605450M/1110/a4) — FY2027 46.6
- Support — FY2027 6.0
- Management Services — FY2027 2.1

## Source & machine access

- **Source:** FY2027 Department of the Navy RDT&E Budget Justification, Exhibit R-2A, PE 0605450M project 1110 (PB PB2027). Narrative is the government's own text.
- **No marks, no contractors at this grain** — congressional marks land on the program element and R-3 performers on the project.
- **MCP:** `mcp.hitchintel.com` — `budget_get_activity`.

*HitchAI is an independent intelligence service, not affiliated with the U.S. Department of Defense. Budget figures are requests/estimates, not obligations.*