> **RESTART.** Funded in FY2025 ($20.1M), zeroed in FY2026, $22.6M requested again in FY2027.

## Summary

This activity requests $22.6M in FY2027, 14% of project 3067 — a restart, funded in FY2025 and zeroed in FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

## What the FY2027 request buys

**FY2027 planned work.** FY2027 efforts will focus on continued maturation of the Medium Unmanned Surface Vehicle (MUSV) prototype build, leveraging commercial solutions. In parallel, the initial MUSV Program of Record (PoR) EDM delivery is scheduled for late Q2 FY2027, followed by EDM installation, integration, and testing in Q4 FY2027. These activities will include implementation of all required cybersecurity and cryptographic capabilities. Additionally, FY2027 efforts will support the continued maturation of the ORIENT-like solution developed under DIU initiatives, with the next iteration planned for delivery in Q4 FY2027. This solution will provide resilient C4I capabilities designed to support mass deployment of RAS platforms and ensure secure communications in denied, degraded, intermittent, and low-bandwidth (DDIL) environments.

**FY2026 to FY2027 change.** FY27: +$22.6M to support expansion of MUSV and sUSV production and amplified requirements under PAE RAS

## Before the request year

**FY2026 plans — current year.** Although Project 3067 was zeroed in PB26, the accomplishments below reflect work executed under PB25 funding, with some activities continuing into early FY26.

## Funding

| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 20.1 |
| FY2026 | Enacted | 0.0 |
| FY2027 | Request | 22.6 |

> Prior, current and budget year only — an R-2A activity carries no five-year plan. It sums exactly into its project in the request year and not necessarily in any other.

## Other activities in project 3067

- [Mission and Collaborative Autonomy](https://hitchintel.com/programs/0605513N/3067/a1) — FY2027 35.5
- Adjunct Remote Engagement System (ARES) — FY2027 28.7
- [Perception Automatic Target Recognition and Track Management](https://hitchintel.com/programs/0605513N/3067/a2) — FY2027 28.2
- [Autonomous Command & Control](https://hitchintel.com/programs/0605513N/3067/a4) — FY2027 23.4
- [RAS Software & Cloud Infrastructures](https://hitchintel.com/programs/0605513N/3067/a5) — FY2027 13.8
- Management Services — FY2027 4.5

## Source & machine access

- **Source:** FY2027 Department of the Navy RDT&E Budget Justification, Exhibit R-2A, PE 0605513N project 3067 (PB PB2027). Narrative is the government's own text.
- **No marks, no contractors at this grain** — congressional marks land on the program element and R-3 performers on the project.