R-2A Activity · President's Budget PB2027

B/L 2.1 INTEGRATION AND FOT&E TESTING

FY2027 Request
$10.2M
▼ 7.9% vs FY2026
HitchAI read

This activity requests $10.2M in FY2027, 20% of project 2039, down 7.9% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$10.2M
▼ 7.9% vs FY2026
FY2026 Enacted
$11.1M
▼ 6.7% vs FY2025
FY2025 Actual
$11.8M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 2039 of PE 0607658N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Continue DT-C1 of CEC Increment 2 Block II Capability Group 3 in multiple shipboard, airborne, and land mobile combat system configurations. Continue planning for DT-C2 of Increment 2 Block II capabilities. Complete OT-D3 of CEC AN/USG-2B on DDG 1000.

FY2026 to FY2027 change

Decrease is due to minor pricing differences

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

Continue DT-C1 of initial CEC Increment 2 Block II capabilities in multiple shipboard, airborne, and land mobile combat system configurations. Continue planning for DT-C2 of Increment 2 Block II capabilities. Conduct events for OT-D3 of CEC AN/USG-2B on DDG 1000.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

011.8FY25ACTUAL11.1FY26ENACTED10.2FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual11.8
FY2026Enacted11.1
FY2027Request10.2

This activity is 20% of project 2039's FY2027 request and 8.4% of PE 0607658N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

9 activities in project 2039

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

B/L 2.1 INTEGRATION AND FOT&E TESTING — this activity$10.2M ▼ 8%
SYSTEM IMPROVEMENTS$8.8M ▼ 15%
FIELD ACTIVITIES$8.0M ▼ 2%
PROGRAM PROTECTION$7.5M ▼ 21%
NAVAL INTEGRATED FIRE CONTROL-COUNTER AIR (NIFC-CA)$5.0M ▼ 23%
E-2D$5.0M ▼ 10%
CEC CYBER RESILIENCY$4.7M ▼ 4%
ENTERPRISE AIR SURVEILLANCE RADAR (EASR)$1.3M ▼ 70%
ANTENNA DEVELOPMENT$0.0M
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0607658N, project 2039 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0607658N/2039/a1.md · MCP mcp.hitchintel.combudget_get_activity