RDT&E Project · President's Budget PB2027

Unified Data Library (UDL)

Project 673941·PE 1203940SF — Space Situation Awareness Operations·U.S. Space Force·BA7
FY2027 Request
$0.0M
▼ 100% vs FY2026
HitchAI read

Project 673941 — Unified Data Library (UDL) requests $0.0M in FY2027, 0.0% of the $294.9M requested for program element 1203940SF, down 100% on FY2026. 1 R-2A activity decomposes the request.

FY2027 Request
$0.0M
▼ 100% vs FY2026
FY2026 Enacted
$42.2M
▲ 22% vs FY2025
FY2025 Actual
$34.8M
Prior year
Project detail

What project 673941 buys

NOTE: In FY2027+ UDL funds have transferred to a new Program Element (PE) 1203156SF, Project (673941), Unified Data Library (UDL). The Unified Data Library project (673941) supports integration, exploitation, and delivery of Space Domain Awareness (SDA) data sources for Command and Control (C2) and battle management of space forces. It focuses on enabling data sharing, establishing the data architecture required to aggregate multi-sensor data for broader use at different classification levels, transforming any-source data into normalized, usable information via data exploitation tools, followed by data hand off to Battle Management Command and Control mission systems to support actual space operations. The UDL will directly connect to dedicated USSF collateral, contributing and non-traditional sensors and systems with modernized interfaces and transport options to broadly expose data. The UDL will be the single source for accessing and managing all data in support of the USSF, providing a central location to find and access data, enabling superior analytics. This program may include necessary civilian pay expenses required to manage, execute, and deliver the weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program elements 1206392SF and 1206398SF.

R-3 lines of work
  • Product Development
  • Test and Evaluation
  • Management Services
Funding trajectory

Project 673941 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

25034.8FY25ACTUAL42.2FY26ENACTED0.0FY27REQUEST0.0FY280.0FY290.0FY300.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual34.8
FY2026Enacted42.2
FY2027Request0.0
FY2028Outyear0.0
FY2029Outyear0.0
FY2030Outyear0.0
FY2031Outyear0.0
Inside the project

1 accomplishment / planned program

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Coverage is partial across the corpus, so count activities, never total them.

Unified Data Library (UDL)▼ 100%
FY2025 actual$34.8M
FY2026 enacted$42.2M
FY2027 request$0.0M

FY2027 planned work FY 2027 plans are under the new Data Transport and Networking Program (1203156SF).

FY2026 plans — current year Upgrade the UDL Platform Architecture to boost ingestion, storage, and exposure of data to meet warfighter needs. In support of kill chain closure, the UDL has prioritized the following systems for ingestion into the UDL in FY 2026: Bounty Hunter, Deep Space Advanced Radar Capability (DARC), SILENTBARKER, Joint Commercial Operations, Ground-Based Electro-Optical Deep Space Surveillance (GEODSS), Space Surveillance Telescope, C-Band Space Surveillance Radar System, Geosynchronous Space Situational Awareness, and Eglin Radar. Continue to expand UDL infrastructure to maintain digital superiority, support an increased number of providers and consumers and operations across multiple security…