RDT&E Project · President's Budget PB2027

B-52 CERP

Project 675129·PE 0101113F — B-52 Squadrons·U.S. Air Force·BA7
FY2027 Request
$998.6M
▲ 68% vs FY2026
HitchAI read

Project 675129 — B-52 CERP requests $998.6M in FY2027, 68% of the $1.48B requested for program element 0101113F, up 68% on FY2026. 1 R-2A activity decomposes the request. Boeing is the largest named R-3 performer at $897.0M, 90% of the project's FY2027 R-3 total.

FY2027 Request
$998.6M
▲ 68% vs FY2026
FY2026 Enacted
$595.7M
▼ 21% vs FY2025
FY2025 Actual
$753.4M
Prior year
Project detail

What project 675129 buys

The B-52J Commercial Engine Replacement Program (CERP) supports nuclear and conventional operations by replacing the current TF33-PW-103 engine on the B-52H aircraft. The TF33-PW-103 engine is experiencing significant supportability challenges due to diminished manufacturing sources and obsolescent technologies. This program will replace the current TF33-PW-103 engine with new military derivative commercial Rolls-Royce F130 engines of similar size, weight, and thrust characteristics. Along with the new engines, CERP will replace associated subsystems, such as engine struts and nacelles, the electrical power generation system, and cockpit displays. The development, production and installation of new engines and related subsystems will replace the legacy equipment on all 76 B-52H aircraft. Any B-52H aircraft modified with the new commercial engines and associated subsystems will be designated as B-52J. B-52J CERP is taking advantage of advances in technology and on-going development efforts to acquire engines and integrate them into the B-52. The new technology will increase both the overall reliability and maintainability of the propulsion system and produce additional electrical power generation capabilities for emerging requirements. The B-52J CERP will allow the operational command (Air Force Global Strike Command) to fully utilize the capabilities of the B-52 aircraft to employ an array of nuclear and conventional weapons while increasing fuel efficiency and extending the range/loiter capabilities of the aircraft. In addition, applicable training devices must be developed, modified and/or upgraded in conjunction with the aircraft modifications. As B-52J CERP brings additional capability to the B-52, emerging security/certification requirements (nuclear hardening, cyber security, program protection, etc.) are being addressed. Several concurrent aircraft upgrades during the B-52J CERP necessitate temporary facilities or facility upgrades/modifications. In addition, the upgrades may necessitate studies be performed to determine optimal engine installation and deployment options. Additionally, funds will be used to procure long lead material and installation for test aircraft to include engines and all required associated components in the B-52J CERP configuration baseline (i.e. RMP A & B EMD kits).

R-3 lines of work
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
Funding trajectory

Project 675129 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

2505007501,0000753.4FY25ACTUAL595.7FY26ENACTED998.6FY27REQUEST1,068.9FY28849.7FY29666.7FY30674.5FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual753.4
FY2026Enacted595.7
FY2027Request998.6
FY2028Outyear1,068.9
FY2029Outyear849.7
FY2030Outyear666.7
FY2031Outyear674.5
Inside the project

1 accomplishment / planned program

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Each describes FY2027 work in enough detail to have its own page; the rest are shown here in full. Coverage is partial across the corpus, so count activities, never total them.

B-52 CERP▲ 68%
FY2025 actual$753.4M
FY2026 enacted$595.7M
FY2027 request$998.6M

Continue execution of the Post-CDR Development contract. Continue ordering hardware for two test aircraft on material contracts and deliver necessary components to modify the aircraft. Continue F130 engine integration testing. Begin modification of test aircraft.

Read the FY2027 plan →
Who's building it

Named performers on project 675129

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

Boeing
$897.0M · 90%
AFLCMC/FZA
$21.0M · 2.1%
412TW
$15.2M · 1.5%
Rolls Royce
$12.8M · 1.3%