What project 672985 buys
Minuteman (MM) III Support Equipment program designs, develops, and tests replacement of obsolete/non-serviceable weapon system support equipment. These programs will also implement processes, procedures, and data systems to mitigate the transition risk from MM III to Sentinel. Efforts include design, development, and testing of support equipment such as LGM-30G MM III Acquisition of Transportation & Handling (MATH), 2nd Gen PSRE Transport Trailer (PTT2), 4th Gen Rocket Motor Semi-Trailer (RMS4), Missile Transporter Acquisition Procurement (MTAP), and Fourth Generation Transporter Erector (TE4) efforts. MM Support Equipment also includes unforeseen costs arising for various reasons for programs from prior President's Budgets. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such programs funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, 0606398F.
- Product Development
- Support
- Test and Evaluation
- Management Services
Project 672985 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 10.4 |
| FY2026 | Enacted | 20.9 |
| FY2027 | Request | 25.2 |
| FY2028 | Outyear | 52.0 |
| FY2029 | Outyear | 51.0 |
| FY2030 | Outyear | 34.0 |
| FY2031 | Outyear | 27.0 |
4 accomplishments / planned programs
The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Coverage is partial across the corpus, so count activities, never total them.
FY2027 planned work - Prime Contractor PDR - Sub Contractor(s) CDR - Prime Contractor CDR
FY2026 to FY2027 change Ramp up in development and initiation of testing.
FY2026 plans — current year - TDP updates - System Requirements Review (SRR) - System Functional Review (SFR) - Sub Contractor(s) Preliminary Design Review (PDR)
FY2027 planned work - RFP Release, Source Selection, Milestone B approval - 4QFY27 contract award - System Requirements Review / System Functional Review
FY2026 to FY2027 change Funding decrease is due to change in acquisition strategy.
FY2026 plans — current year MDA approval of Acquisition Strategy and continue RFP development.
FY2027 planned work -Obtain MDA approval of Acquisition Strategy -Release Request for Proposal
FY2026 to FY2027 change New Start for FY2027.
FY2027 planned work RFP Release, Source Selection, Milestone B approval.
FY2026 to FY2027 change Funding decrease is due to change in acquisition strategy.
FY2026 plans — current year MDA approval of Acquisition Strategy and continue RFP development.
Named performers on project 672985
Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.