RDT&E Program Element · President's Budget PB2027

Minuteman Squadrons

PE 0101213F·U.S. Air Force·Approp. 3600 — RDT&E·BA7 — Operational System Development
FY2027 Request
$79.3M
Air Force · RDT&E
HitchAI read

U.S. Air Force requests $79.3M in FY2027, sustained across the five-year plan. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators funded it in full. NG leads the industry work.

FY2027 Request
$79.3M
▲ 15% vs FY2026
FY2026 Enacted
$69.1M
▲ 21% vs FY2025
FY2025 Actual
$57.2M
Prior year

Roll-up of 3 projects. Projects are the summable leaves — the PE total is their sum, never added to it.

For fiscal year 2027, the U.S. Air Force is requesting $79.3M for Minuteman Squadrons under RDT&E program element 0101213F, up 15% over FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

255075100125057.2FY25ACTUAL69.1FY26ENACTED79.3FY27REQUEST126.1FY28129.3FY29112.7FY3091.8FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual57.2
FY2026Enacted69.1
FY2027Request79.3
FY2028Outyear126.1
FY2029Outyear129.3
FY2030Outyear112.7
FY2031Outyear91.8
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 7 — Operational System Development.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Complete
Prototyping
BA 4
Current
Development & Fielding
BA 5–7
Inside the program element

3 projects roll up into PE 0101213F

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves 15% overall, which can hide much larger swings below.

Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$79.3M
House NDAA (HASC)HASC
$79.3M full · +$0
Senate NDAA (SASC)SASC
$79.3M full · +$0
House Approps (HAC-D)HAC_D
$418.2M full · +$0
▲ $338.9M chamber gap — unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

NG
$19.4M · 24%
MM III Missile Transporter Acquisition Procurement (MTAP) · CPFF
Hill AFB
$11.7M · 15%
LGM-30G Stage 1 Battery (SOBR) · CPIF
Where FY2027 funding flowsShare$M
Industry primes78%62.1
Other / unspecified22%17.3
FY2027 request100%79.3
See NG's full federal contract ledger members
Program detail

Mission & acquisition strategy

The Minuteman (MM) Ground and Communication Equipment program replaces obsolete/unsupportable ground-based weapon system equipment located at 45 Launch Control Centers (LCCs) and 450 Launch Facilities (LFs) necessary to continue Minuteman III (MM III) operations until replaced by Sentinel. Current efforts include development, qualification, integration, and testing of replacement equipment for the LGM-30G Fast Rising B-Plug Energy Storage System-Replacement (FRBP ESS-R). MM III Baseline Support program replaces or upgrades obsolete/unsupportable MM III equipment critical for continued system operations.

Ground and communication equipment replacement efforts are reviewed to determine the best method for execution, including vendor qualification and procurement with no development required, develop and/or modify organic depot capabilities with industry. Industry development for ground and communication equipment efforts will be assessed for scope determination on existing contracts to streamline procurement activities, and where needed, competitive source selections will be executed. Nuclear Surety Cross Check Analysis (NSCCA) and Independent Verification and Validation (IV&V) efforts are contracted separately. Nuclear Surety and Vulnerability analysis requirements are covered in the Acquisition Strategy.

Project 672984, 672985, 672983 — MM III Baseline Support
  • Product Development
  • Test and Evaluation
  • Management Services
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?Which project inside PE 0101213F is growing fastest, and which is shrinking?How is the FY2027 request split between industry and government performers?

This page carries the budget justification and the NDAA marks — nothing else. For what NG has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Air Force RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0101213F (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Minuteman Squadrons (PE 0101213F)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0101213F
Machine access
Markdown twin /programs/0101213F.md · MCP mcp.hitchintel.combudget_get_program_element, budget_get_cong_marks
FY2027 Request
$49.8M
▲ 16% vs FY2026
FY2026 Enacted
$42.8M
▼ 8.5% vs FY2025
FY2025 Actual
$46.8M
Prior year

MM III Baseline Support — one RDT&E project inside PE 0101213F. Congressional marks are recorded on the program element, not on a project.

Project 672984 — MM III Baseline Support — requests $49.8M in FY2027, 63% of the $79.3M requested for program element 0101213F. Year over year it grows 16% against FY2026.

Funding trajectory

Project 672984 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

255075046.8FY25ACTUAL42.8FY26ENACTED49.8FY27REQUEST74.1FY2878.3FY2978.7FY3064.8FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual46.8
FY2026Enacted42.8
FY2027Request49.8
FY2028Outyear74.1
FY2029Outyear78.3
FY2030Outyear78.7
FY2031Outyear64.8
Inside the project

7 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

Little Mountain Test Facility (LMTF)NEW
FY2025 actual$0.0M
FY2026 enacted$0.0M
FY2027 request$5.7M

LMTF is not an FY2027 new start. FY2026 and prior efforts were previously funding in ADSR, FT3 and MTAP. FY2027 efforts will continue the development of additional test capability for current and future nuclear enterprise. LMTF Large Flash X-Ray (LFXR) customers require upgraded capabilities with the Advanced Radiation Environment…

Stage 1 Battery Replacement (SOBR)▲ 79%
FY2025 actual$3.1M
FY2026 enacted$8.6M
FY2027 request$15.3M

- Critical Design Review (CDR) - Technical Readiness Review (TRR) - Begin Qual Testing

LGM-30G Flight Test Telemetry and Termination System (FT3)▼ 77%
FY2025 actual$19.7M
FY2026 enacted$16.9M
FY2027 request$3.9M

- Continue to close out redesign/requalification engineering activities and obtain critical engineering data approval - Start to close out the contract

LGM-30G Higher Authority Communication Test System (HACTS) 2.0▲ 169%
FY2025 actual$0.0M
FY2026 enacted$2.1M
FY2027 request$5.6M

- Continue System Integration Test (SIT) - Conduct Test Readiness Review (TRR) - Conduct Functional Configuration Audit / Physical Configuration Audit (FCA/PCA) - Milestone C 4QFY2027

LGM-30G Depot Reentry Support Equipment Replacement Program (DRSERP)▲ 145%
FY2025 actual$16.5M
FY2026 enacted$6.8M
FY2027 request$16.7M

- Conduct Mk12A TPS PDR (Jun 2027) - Conduct Mk12A VDATS Hardware CDR (Nov 2026) - Award Service STAR TPS/VDATS contract

LGM-30G Arm/Disarm Switch Replacement (ADSR)▼ 52%
FY2025 actual$0.0M
FY2026 enacted$3.5M
FY2027 request$1.7M

Continue qualification testing to finalize development effort.

LGM-30G Baseline Support▼ 83%
FY2025 actual$7.5M
FY2026 enacted$5.0M
FY2027 request$0.8M

- Continue to conduct studies of system performance - Continue to conduct cost trades and acquisition planning activities, up to and including proposal preparation, technology for future capabilities - Conduct Subsystem Critical Design Reviews - Conduct System-level Critical Design Review - Conduct Stress Testing - EMD Contract Award

Project 672984 — every activity in full →
Who's building it

Named performers on project 672984

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

Hill AFB
$11.7M · 24%
402nd/581st SWES
$9.4M · 19%
AFLCMC/ROA
$4.9M · 10.0%
General Dynamics
$4.2M · 8.4%
Project detail

What project 672984 buys

Minuteman III (MM III) Baseline Support program replaces or upgrades obsolete/unsupportable flight test unique equipment installed on the missile during flight test, used to test MM III systems on the ground, or located at test facilities to collect, process, and analyze test data. Flight test equipment supports test and evaluation of MM III capabilities, and MM III Operational Test Launches (OTLs) to determine ICBM force readiness, reliability, and capability shortfalls. Efforts include development, qualification, integration and testing of replacement equipment such as LGM-30G Flight Test, Telemetry, and Termination System (FT3), LGM-30G Higher Authority Command Test System (HACTS) 2.0, LGM-30G Stage 1 Battery Replacement (SOBR), LGM-30G Little Mountain Test Facility (LMTF), LGM-30G Depot Reentry Support Equipment Replacement Program (DRSERP), and Arm/Disarm Switch Replacement (ADSR). As other similar equipment is identified for replacement, it will be added to this program. MM III Baseline Support also provides for other MM III unique government costs, studies of system performance, contract closeout costs, cost trades and acquisition planning activities, up to and including proposal preparation, to meet Capability Development Document requirements in an evolving threat landscape by leveraging advanced technologies. MM III Baseline Support also includes unforeseen costs arising for various reasons for programs from prior President's Budgets. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such programs funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, 0606398F.

R-3 lines of work
  • Product Development
  • Test and Evaluation
  • Management Services
FY2027 Request
$25.2M
▲ 21% vs FY2026
FY2026 Enacted
$20.9M
▲ 100% vs FY2025
FY2025 Actual
$10.4M
Prior year

MM Support Equip — one RDT&E project inside PE 0101213F. Congressional marks are recorded on the program element, not on a project.

Project 672985 — MM Support Equip — requests $25.2M in FY2027, 32% of the $79.3M requested for program element 0101213F. Year over year it grows 21% against FY2026.

Funding trajectory

Project 672985 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

2550010.4FY25ACTUAL20.9FY26ENACTED25.2FY27REQUEST52.0FY2851.0FY2934.0FY3027.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual10.4
FY2026Enacted20.9
FY2027Request25.2
FY2028Outyear52.0
FY2029Outyear51.0
FY2030Outyear34.0
FY2031Outyear27.0
Inside the project

4 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

LGM-30G MM III Missile Transporter Acquisitions Program (MTAP)▲ 72%
FY2025 actual$6.3M
FY2026 enacted$12.5M
FY2027 request$21.4M

- Prime Contractor PDR - Sub Contractor(s) CDR - Prime Contractor CDR

MATH 2nd Generation Propulsion System Rocket Engine Transport Trailer Program (PTT2)▼ 93%
FY2025 actual$2.1M
FY2026 enacted$4.2M
FY2027 request$0.3M

RFP Release, Source Selection, Milestone B approval.

MATH Rocket Motor Semitrailer Program (RMS4)▼ 25%
FY2025 actual$2.1M
FY2026 enacted$4.2M
FY2027 request$3.1M

- RFP Release, Source Selection, Milestone B approval - 4QFY27 contract award - System Requirements Review / System Functional Review

LGM-30G Fourth Generation Transport Erector (TE4)NEW
FY2025 actual
FY2026 enacted$0.0M
FY2027 request$0.3M

-Obtain MDA approval of Acquisition Strategy -Release Request for Proposal

Project 672985 — every activity in full →
Who's building it

Named performers on project 672985

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

NG
$19.4M · 77%
BAE
$1.7M · 7.0%
LDTO
$0.1M · 0.3%
Project detail

What project 672985 buys

Minuteman (MM) III Support Equipment program designs, develops, and tests replacement of obsolete/non-serviceable weapon system support equipment. These programs will also implement processes, procedures, and data systems to mitigate the transition risk from MM III to Sentinel. Efforts include design, development, and testing of support equipment such as LGM-30G MM III Acquisition of Transportation & Handling (MATH), 2nd Gen PSRE Transport Trailer (PTT2), 4th Gen Rocket Motor Semi-Trailer (RMS4), Missile Transporter Acquisition Procurement (MTAP), and Fourth Generation Transporter Erector (TE4) efforts. MM Support Equipment also includes unforeseen costs arising for various reasons for programs from prior President's Budgets. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such programs funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, 0606398F.

R-3 lines of work
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
FY2027 Request
$4.4M
▼ 19% vs FY2026
FY2026 Enacted
$5.4M
No FY2025 funding
FY2025 Actual
$0.0M
Prior year

MM Ground and Comm Equipment — one RDT&E project inside PE 0101213F. Congressional marks are recorded on the program element, not on a project.

Project 672983 — MM Ground and Comm Equipment — requests $4.4M in FY2027, 5.5% of the $79.3M requested for program element 0101213F. Year over year it falls 19% against FY2026.

Funding trajectory

Project 672983 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

00.0FY25ACTUAL5.4FY26ENACTED4.4FY27REQUEST0.0FY280.0FY290.0FY300.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual0.0
FY2026Enacted5.4
FY2027Request4.4
FY2028Outyear0.0
FY2029Outyear0.0
FY2030Outyear0.0
FY2031Outyear0.0
Inside the project

1 accomplishment / planned program

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

LGM-30G Fast Rising B-Plug Energy Storage System-Replacement (FRBP ESS-R)▼ 19%
FY2025 actual$0.0M
FY2026 enacted$5.4M
FY2027 request$4.4M

FY2027 planned work ESS: Functional Configuration Audit (FCA), Physical Configuration Audit (PCA), and Milestone C. Support Equipment (SE): Conduct CDR and prepare for TRR.

FY2026 to FY2027 change Due to the level of MICAPs with the legacy system, great strides are being made to expedite the FRBP schedule. Recent schedule saving initiatives allow for production and fielding activities a year earlier, while still delivering a quality product to the Warfighter. The Energy Storage System (ESS) is further along in the engineering process and has been decoupled from the Support Equipment (SE) in the program schedule. ESS EMD to complete 2QFY28 and SE EMD to complete 4QFY29.

FY2026 plans — current year Energy Storage System (ESS): Conduct Critical Design Review (CDR), Test Readiness Review (TRR), and Qualification Testing (QT). Support Equipment (SE): Conduct PDR and prepare for CDR.

Who's building it

Named performers on project 672983

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

Select Engineering Serv
$3.5M · 80%
BAE
$0.6M · 13%
LDTO
$0.1M · 1.6%
Project detail

What project 672983 buys

The MM Ground and Comm Equipment program replaces obsolete/unsupportable ground-based weapon system equipment located at Launch Control Centers (LCCs) and Launch Facilities (LFs) necessary to continue Minuteman III operations until replaced by Sentinel. Current efforts include development, qualification, integration, and testing of replacement equipment such as the LGM-30G Fast Rising B-Plug Energy Storage System-Replacement (FRBP ESS-R). MM Ground and Comm Equipment also includes unforeseen costs arising for various reasons on programs from prior President's Budgets. This program element may include necessary civilian pay expenses required to manage, execute, and deliver weapon system capability. The use of such programs funds would be in addition to the civilian pay expenses budgeted in program element 0605827F, 0605828F, 0605829F, 0605831F, 0605832F, 0605833F, 0605898F, 0606398F.

R-3 lines of work
  • Product Development
  • Test and Evaluation
  • Management Services