RDT&E Project · President's Budget PB2027

AMPV Improvement Program

FY2027 Request
$10.9M
▲ 14% vs FY2026
HitchAI read

Project DD4 — AMPV Improvement Program requests $10.9M in FY2027, 2.2% of the $492.4M requested for program element 0203735A, up 14% on FY2026. 2 R-2A activities decompose the request.

MarketsGround Combat VehiclesGround Vehicles (mfg)

Matched on this project's title. A title match, not a curated taxonomy — narrative-only matches are not shown at all rather than shown with a caveat nobody reads. No market size is quoted here: a market spans appropriations far beyond this program element.

FY2027 Request
$10.9M
▲ 14% vs FY2026
FY2026 Enacted
$9.5M
▼ 20% vs FY2025
FY2025 Actual
$11.9M
Prior year
Project detail

What project DD4 buys

The Armored Multi-Purpose Vehicle (AMPV) is an ACAT IC program designed to replace the Army's Armored Personnel Carrier (M113) Family of Vehicles (FoV) within the Armored Brigade Combat Team (ABCT). The AMPV addresses current and future capability gaps in the Vietnam-era M113 Family of Vehicles by delivering enhanced mobility, lethality, network communication/interoperability, and protection. These advancements are essential for moving personnel and executing key mission roles on the battlefield within the ABCT. Fielding is currently underway and is expected to continue through FY2042. The AMPV Improvement Program focuses on upgrading capabilities for integration and implementation across the AMPV FoV to enhance mission effectiveness. FY 2027 funding of $10.853 million for Project DD4 supports Army-requested changes, as well as the continued development, testing, and integration of the following initiatives: * Composite Rubber Track (CRT): Provides significant advantages over traditional linked steel tracks, including vehicle weight reduction, improved fuel economy, enhanced track and road wheel durability, and reduced soldier maintenance requirements. * Vehicular Situational Awareness: Enhances driver and vehicle commander visibility around the vehicle, creating a safer operating environment. * Counter-Unmanned Aerial System (C-UAS) Solutions: Improves AMPV survivability in contested environments by neutralizing UAS threats. * Predictive Logistics Tools: Utilizes analytics and artificial intelligence to forecast supply chain needs, reducing vehicle downtime in contested environments. * Mission Equipment Packages (MEPs): Enables rapid configuration of the AMPV to meet evolving operational requirements across its five variants. Specifically, the turreted mortar MEP will significantly enhance the legacy mortar solution inherited from the M113 M1064 variants. Additionally, the AMPV Improvement Program supports Army assessments, experimentation, and testing to address emerging requirements that impact the AMPV platform.

R-3 lines of work
  • Product Development
  • Support
Funding trajectory

Project DD4 funding, FY2025–FY2028

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

011.9FY25ACTUAL9.5FY26ENACTED10.9FY27REQUEST10.8FY28
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual11.9
FY2026Enacted9.5
FY2027Request10.9
FY2028Outyear10.8
Inside the project

2 accomplishments / planned programs

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. 1 of them describes FY2027 work in enough detail to have its own page; the rest are shown here in full. Coverage is partial across the corpus, so count activities, never total them.

FY2025 actual$11.0M
FY2026 enacted$8.7M
FY2027 request$10.0M

Conduct system level integration and engineering efforts to upgrade and design mobility, survivability, reliability, software, and lethality upgrades. Continue trade studies, market surveys, select and demonstrate enhanced AMPV capabilities to include Contested Logistics, C-UAS, CRT, Segmented CRT, Vehicular Situational Awareness, MEPs…

Read the FY2027 plan →
Program Management Office (PMO) Support▼ 2%
FY2025 actual$0.8M
FY2026 enacted$0.9M
FY2027 request$0.8M

FY2027 planned work Systems Engineering and Program Management support (labor, travel, training, supplies, and equipment) for Research, Development, Test, & Evaluation efforts related to emerging Army requirements impacting the AMPV design.

FY2026 to FY2027 change Funding decrease is due to economic adjustment.

FY2026 plans — current year Systems Engineering and Program Management support (labor, travel, training, supplies, and equipment) for Research, Development, Test, & Evaluation efforts related to emerging Army requirements impacting the AMPV design.

FY2025 accomplishments Systems Engineering and Program Management support (labor, travel, training, supplies, and equipment) for Research, Development, Test, & Evaluation (RDT&E) efforts related to emerging Army requirements impacting the AMPV design.