R-2A Activity · President's Budget PB2027

SSF: Product Development

FY2027 Request
$11.5M
◆ New start in FY2027
HitchAI read

This activity requests $11.5M in FY2027, 30% of project 2275 — a new start with no prior-year and no current-year money. The R-2A exhibit describes it across FY2027, including what the FY2027 money is planned to buy.

New start

This activity requests $11.5M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

FY2027 Request
$11.5M
No FY2026 funding
FY2026 Enacted
$0.0M
No FY2025 funding
FY2025 Actual
$0.0M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 2275 of PE 0206313M. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

- Continue enhancements to SSF user interface by increasing functionality and user experience. - Continue SSF interoperability with the Electromagnetic Battle Management-Joint (EMBM-J) Enterprise capability. - Continue sensor integration of SSF with organic Marine Corps sensors. - Continue development of communications planning and tools within the SSF user interface. - Continue research and integration efforts with artificial intelligence and machine learning tools to support the classification of EMS data for Electronic Sensing and Attack (ES/EA) and development of Course of Action (COA) tools that can model synchronization of EA effects. - Complete integration of Host Nation Spectrum Worldwide Database (HNSWD) which provides guidance to spectrum managers on allocated spectrum and frequencies which are authorized and prohibited in the host country(s). - Initiate integration with Defense Information System Agency Spectrum XXI modernization efforts. - Initiate integration of SSF into the Marine Corps' organic cloud hosting environment. - Initiate integration of SSF ingest services into the Marine Corps data orchestration layer to enable near real time sharing of spectrum data with command-and-control systems. - Initiate development of training capability to enable SSF capabilities in training environments while leveraging live, virtual, and constructive training data.

FY2026 to FY2027 change

Increase from FY26 to FY27 reflects initiation of integration with Marine Corps data orchestration layer and cloud hosting environment and initiation of development for of training capability to enable SSF capabilities in training environments while leveraging live, virtual, and constructive training data. SSF transitions from 0206625M to 0206313M in FY27.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

00.0FY25ACTUAL0.0FY26ENACTED11.5FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual0.0
FY2026Enacted0.0
FY2027Request11.5

This activity is 30% of project 2275's FY2027 request and 4.3% of PE 0206313M's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

17 activities in project 2275

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

TCM: Product Development$17.7M ▲ 132%
SSF: Product Development — this activity$11.5M NEW
TCM: Engineering and Program Support$4.2M ▲ 33%
WSATCOM: Product Development$2.5M flat
WSATCOM: Test and Evaluation$0.9M ▲ 24%
NOTM: Test and Evaluation Support$0.7M ▲ 3%
NOTM: Product Development$0.5M ▲ 4%
TEEE: Test & Evaluation$0.5M ▲ 1%
WSATCOM: Engineering and Program Support$0.2M ▲ 2%
TCM: Management Services$0.0M ▼ 100%
ERS: Product Development$0.0M ▼ 100%
ERS: Engineering and Program Support$0.0M ▼ 100%
ERS: Test and Evaluation Support$0.0M ▼ 100%
WSATCOM: Management Services$0.0M
TWTS: Product Development$0.0M ▼ 100%
TWTS: Test and Evaluation$0.0M ▼ 100%
Golding: Product Development$0.0M ▼ 100%
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0206313M, project 2275 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access