Project 673041 — ICBM MEECN Terminals (IMT) requests $15.8M in FY2027, 6.2% of the $254.8M requested for program element 0303131F — a new start, with no prior-year and no current-year money. 1 R-2A activity decomposes the request, 1 new this cycle.

New start

This project requests $15.8M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

FY2027 Request
$15.8M
No FY2026 funding
FY2026 Enacted
$0.0M
No FY2025 funding
FY2025 Actual
$0.0M
Prior year
Project detail

What project 673041 buys

ICBM MEECN Terminal (IMT) will provide resilient Nuclear Command, Control, and Communications capabilities for the Intercontinental Ballistic Missile (ICBM) Forces. IMT will deliver an integrated NC3 suite which includes Extremely High Frequency (EHF) capabilities and an open architecture-based framework. This framework will enable faster and extensible capabilities integration and upgrades for other communication pathways. IMT will integrate the Common Very Low Frequency (VLF) Receiver (CVR). For ICBM risk reduction, IMT will prepare for integration with ICBM weapon systems. This program element included all necessary expenses required to manage, execute, and deliver weapon system capability. The use of such program funds would be in addition to the civilian pay expenses budgeted in program elements 0605829F, 0605831F, 0605833F, and 0605898F.

R-3 lines of work
  • Product Development
Funding trajectory

Project 673041 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

25507510012500.0FY25ACTUAL0.0FY26ENACTED15.8FY27REQUEST44.8FY2855.2FY2996.7FY30124.2FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual0.0
FY2026Enacted0.0
FY2027Request15.8
FY2028Outyear44.8
FY2029Outyear55.2
FY2030Outyear96.7
FY2031Outyear124.2
Inside the project

1 accomplishment / planned program

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Each describes FY2027 work in enough detail to have its own page; the rest are shown here in full. Coverage is partial across the corpus, so count activities, never total them.

FY2025 actual
FY2026 enacted$0.0M
FY2027 request$15.8M

Work to be accomplished during the next FY includes, but is not limited to, standing up the program office to support the initial development activities of the IMT program, develop the acquisition and contract strategy, assist AFGSC in requirements development, conduct market research and award studies to evaluate industry capabilities…