What project CY50S1 buys
The Data and Sensors Portfolio develops and integrates advanced capabilities that enhance U.S. awareness, decision advantage, and operational readiness in support of Department of War (DoW) contingency plan execution, with a primary focus on the U.S. Indo Pacific Command (USINDOPACOM) area of responsibility. These efforts aim to maintain and restore the comparative U.S. military advantage by improving the collection, fusion, and exploitation of data across multiple domains, enabling timely, precise, and actionable insights for cyber and multi domain operations. Investments in this portfolio reduce operational risk, strengthen deterrence, and ensure the Joint Force can effectively counter emerging and advanced threats in the Indo Pacific region.
- Product Development
Project CY50S1 funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 44.2 |
| FY2026 | Enacted | 117.2 |
| FY2027 | Request | 266.2 |
| FY2028 | Outyear | 42.9 |
| FY2029 | Outyear | 22.7 |
| FY2030 | Outyear | 104.4 |
| FY2031 | Outyear | 113.1 |
1 accomplishment / planned program
The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Each describes FY2027 work in enough detail to have its own page; the rest are shown here in full. Coverage is partial across the corpus, so count activities, never total them.
$266.173M in FY 2027 funding will mature the Command’s Data Analytic Support Cell (DASC), enabling the use of advanced analytical tools aligned to mission threads and an analytic scheme of maneuver to improve command and control of the DCDC. Additionally, FY 2027 resources will sustain existing USINDOPACOM capabilities installed from FY…
Read the FY2027 plan →Named performers on project CY50S1
Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.