R-2A Activity · President's Budget PB2027

Burn n' Go

FY2027 Request
$18.7M
▼ 35% vs FY2026
HitchAI read

This activity requests $18.7M in FY2027, 14% of project MSL-01, down 35% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$18.7M
▼ 35% vs FY2026
FY2026 Enacted
$28.8M
In law
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project MSL-01 of PE 0602025E. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

- Conduct assessment of designs to understand ability to meet mass production requirements. - Develop preliminary design of integrated system. - Test sub-scale solid rocket motor assembly. - Compare preliminary designs to potential transition partner requirements.

FY2026 to FY2027 change

The FY 2027 decrease reflects the shift from feasibility testing to sub-scale motor assembly testing.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

- Develop physics models to validate component-level feasibility analysis. - Resolve trade studies for conceptual design. - Validate concept viability for testing and integration phase. - Perform feasibility tests of components for proof-of-concept validation. - Understand system requirements of conceptual design.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25028.8FY26ENACTED18.7FY27REQUEST
Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2026Enacted28.8
FY2027Request18.7

This activity is 14% of project MSL-01's FY2027 request and 1.1% of PE 0602025E's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

8 activities in project MSL-01

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Source
FY2027 Office of the Secretary of Defense RDT&E Budget Justification · Exhibit R-2A · PE 0602025E, project MSL-01 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.