R-2A Activity · President's Budget PB2027

Chemical Processing for Force Protection

FY2027 Request
$12.0M
▼ 58% vs FY2026
HitchAI read

This activity requests $12.0M in FY2027, 9.0% of project MSL-01, down 58% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$12.0M
▼ 58% vs FY2026
FY2026 Enacted
$28.6M
In law
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project MSL-01 of PE 0602025E. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

- Integrate nitrogen oxidation catalysts into a small-scale reactor capable of delivering nitric acid at a particular rate.

FY2026 to FY2027 change

The FY 2027 decrease reflects a shift from heavy system development to integration and testing.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

- Demonstrate system versatility with exposure to a broader range of usable, raw material inputs to generate an increased number of energetic material outputs. - Administer energetic material synthesis demonstrations at an increasing scale. - Execute additional end-to-end validation testing on energetic materials developed from system level demonstrations. - Conduct a critical design review based on outcomes from demonstrations and validation tests on modular platforms. - Demonstrate sub-scale production capability on modular platforms. - Synthesize energetic materials from program-developed database of precursors at a pilot scale. - Develop direct nitrogen oxidation catalysts capable of achieving a high reaction rate at low energy.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25028.6FY26ENACTED12.0FY27REQUEST
Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2026Enacted28.6
FY2027Request12.0

This activity is 9.0% of project MSL-01's FY2027 request and 0.7% of PE 0602025E's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

8 activities in project MSL-01

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Source
FY2027 Office of the Secretary of Defense RDT&E Budget Justification · Exhibit R-2A · PE 0602025E, project MSL-01 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.