R-2A Activity · President's Budget PB2027

(U) Science & Tech Management - ONR Field Acts

FY2027 Request
$62.2M
▼ 14% vs FY2026
HitchAI read

This activity requests $62.2M in FY2027, 100% of project 0000, down 14% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$62.2M
▼ 14% vs FY2026
FY2026 Enacted
$72.1M
▼ 22% vs FY2025
FY2025 Actual
$92.3M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 0000 of PE 0602861N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

This project provides for all labor costs of ONR Headquarters in support of the Navy S&T program. The funds in this project pay the salaries of Scientific and Engineering and corporate business personnel who direct the execution of the Navy's basic research, applied research, and advanced technology development programs at the nation's universities/colleges, Navy laboratories, Warfare Centers, and private industry. This project provides for all basic labor costs of ONR activities in support of the entire Navy S&T program.

FY2026 to FY2027 change

The FY26 to FY27 reduction is due to OUSW Directed CIVPER Saving.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

This project provides for all labor costs of ONR Headquarters in support of the Navy S&T program. The funds in this project pay the salaries of Scientific and Engineering and corporate business personnel who direct the execution of the Navy's basic research, applied research, and advanced technology development programs at the nation's universities/colleges, Navy laboratories, Warfare Centers, and private industry. This project provides for all basic labor costs of ONR activities in support of the entire Navy S&T program.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

255075092.3FY25ACTUAL72.1FY26ENACTED62.2FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual92.3
FY2026Enacted72.1
FY2027Request62.2

This activity is 100% of project 0000's FY2027 request and 84% of PE 0602861N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

1 activity in project 0000

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

(U) Science & Tech Management - ONR Field Acts — this activity$62.2M ▼ 14%
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0602861N, project 0000 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0602861N/0000/a0.md · MCP mcp.hitchintel.combudget_get_activity