R-2A Activity · President's Budget PB2027

Automated Test and ReTest (ATRT)

FY2027 Request
$37.6M
▲ 88% vs FY2026
HitchAI read

This activity requests $37.6M in FY2027, 100% of project 9B88, up 88% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$37.6M
▲ 88% vs FY2026
FY2026 Enacted
$20.0M
No FY2025 funding
FY2025 Actual
$0.0M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 9B88 of PE 0603598N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

FY 2027 funding is utilized to ramp up execution of crucial Department of the Navy Rapid Capabilities Office (DONRCO) functions necessary for (1) identification of hard problems and capability gaps through coordination and communication with Combatant Commander and Fleet (2) stakeholder engagement to include Warfighter and Industry to identify potential material solutions and (3) execution of Budget Execution-year Technology Selections (BETS) Boards to enable Navy Leadership to make quick, informed decisions on rapidly deployable capability solutions. Efforts include but are not limited to problem definition, analysis, prioritization tool development, industry engagement products, material solution option evaluation, and other specialized products to enable leadership decision and tracking of viable rapid solutions to urgent operational needs.

FY2026 to FY2027 change

FY 2026 to FY 2027 increase of $17.59M supports the ramp up of efforts to include more powerful decision-making tools for Navy Leadership's analysis of viable material solutions, increasing the rigor of identifying capabilities to fill operational gaps and deploy to the warfighter with speed. Further, the use of this funding increases magnitude of modernization training through virtual twin edge analytics centered on a common digital warfighting platform with enterprise sandbox technologies.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

FY 2026 funding is utilized to execute crucial Department of the Navy Rapid Capabilities Office (DONRCO) functions necessary for (1) identification of hard problems and capability gaps through coordination and communication with Combatant Commander and Fleet (2) stakeholder engagement to include Warfighter and Industry to identify potential material solutions and (3) execution of Budget Execution-year Technology Selections (BETS) Boards to enable Navy Leadership to make quick, informed decisions on rapidly deployable capability solutions. Efforts include but are not limited to problem definition, analysis, prioritization tool development, industry engagement products, material solution option evaluation, and other specialized products to enable leadership decision and tracking of viable rapid solutions to urgent operational needs.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

2500.0FY25ACTUAL20.0FY26ENACTED37.6FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual0.0
FY2026Enacted20.0
FY2027Request37.6

This activity is 100% of project 9B88's FY2027 request and 43% of PE 0603598N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

1 activity in project 9B88

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Automated Test and ReTest (ATRT) — this activity$37.6M ▲ 88%
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0603598N, project 9B88 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0603598N/9B88/a0.md · MCP mcp.hitchintel.combudget_get_activity