R-2A Activity · President's Budget PB2027

Network / System Certification and Accreditation (C&A)

FY2027 Request
$21.7M
▲ 19% vs FY2026
HitchAI read

This activity requests $21.7M in FY2027, 100% of project MC11, up 19% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$21.7M
▲ 19% vs FY2026
FY2026 Enacted
$18.3M
▼ 3.0% vs FY2025
FY2025 Actual
$18.8M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project MC11 of PE 0603884C. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

- Ensure compliance with cyber security mandates to maintain continued authorization to operate. - Assess, implement, document, and validate cybersecurity control families for representative systems comprising computing and logic bearing components to support the Development, Test, Training, and Operational Systems.

FY2026 to FY2027 change

- Increase provides for increased testing to ensure cybersecurity compliance.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

- Initiate tier 3 / local control center enhanced cybersecurity data aggregation and analysis capability through deployment of industry standard toolset to improve trend analysis and identification of cross-portfolio threats. - Execution of six (6) developmental cybersecurity test events and six (6) operational cybersecurity test events supporting LRDR, AN/TPY-2, and SBX in order to assess the cyber survivability of Ground Sensors systems in a cyber-contested environment.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

018.8FY25ACTUAL18.3FY26ENACTED21.7FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual18.8
FY2026Enacted18.3
FY2027Request21.7

This activity is 100% of project MC11's FY2027 request and 2.5% of PE 0603884C's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

1 activity in project MC11

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Network / System Certification and Accreditation (C&A) — this activity$21.7M ▲ 19%
Source
FY2027 Office of the Secretary of Defense RDT&E Budget Justification · Exhibit R-2A · PE 0603884C, project MC11 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0603884C/MC11/a0.md · MCP mcp.hitchintel.combudget_get_activity