R-2A Activity · President's Budget PB2027

Joint Laser Weapon System (JLWS)

FY2027 Request
$75.6M
◆ New start in FY2027
HitchAI read

This activity requests $75.6M in FY2027, 95% of project 3402 — a new start with no prior-year and no current-year money. The R-2A exhibit describes it across FY2027, including what the FY2027 money is planned to buy.

New start

This activity requests $75.6M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

FY2027 Request
$75.6M
No FY2026 funding
FY2026 Enacted
$0.0M
No FY2025 funding
FY2025 Actual
$0.0M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 3402 of PE 0603925N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

JLWS N-150-X (Containerized) - Initiate Non-Recurring Engineering (NRE) and incremental procurement of 150 kW class Containerized Laser Weapon System (LWS) - Provide programmatic and technical oversight of contract - Initiate systems engineering, ship and combat system integration requirements development - Initiate development of Ship Installation Drawings (SIDs) and identification/procurement of installation material - Establish Product Support Management (PSM) including In Service Engineering Agent (ISEA) and Software Support Activity (SSA) functions - Initiate development of operation and maintenance documentation for shipboard use JLWS N-500-0 (JBCS) - Continue system design and development based off of Future Naval Capability (FNC) & Office of Secretary of War (OSW) efforts - Initiate system level optical design and testing for Joint Beam Control System (JBCS) - Order additional long lead system level procurements in support of JBCS system design - Continue development of system level Interface Control Drawings (ICDs) and Technical Data Package (TDP) for JBCS - Continue planning for JBCS integration and system test & evaluation activities JLWS N-300-0 (Lethality/Testing) - Initiate lethality-based engineering, testing & analysis, and validation of Directed Energy (DE) modeling & simulation software

FY2026 to FY2027 change

The FY 2026 to FY 2027 increase is for the development of a containerized 150 kW Joint Laser Weapon System (JLWS) for cruise missile defense; incrementally developing and providing at least 300kW of power building on existing laser scaling efforts; development of a Joint Beam Control System (JBCS) 300 kW of power building on existing laser scaling efforts; development of a Joint Beam Control System (JBCS) technology capable of supporting a 300-500kW laser weapon system, and conduct upgrades to the High Energy Laser Counter Anti-Ship Cruise Missile Project (HELCAP) testbed as appropriate to support JLWS testing. In coordination with the Services and the Missile Defense Agency, begin development of a consolidated implementation plan for all Golden Dome Directed Energy projects, leveraging synergy and common weapon architectures between these efforts where possible.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25507500.0FY25ACTUAL0.0FY26ENACTED75.6FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual0.0
FY2026Enacted0.0
FY2027Request75.6

This activity is 95% of project 3402's FY2027 request and 80% of PE 0603925N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

3 activities in project 3402

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Joint Laser Weapon System (JLWS) — this activity$75.6M NEW
SNLWS Government and Support Engineering Services$4.2M RESTART
SNLWS Prime Contractor Efforts$0.0M
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0603925N, project 3402 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.