RDT&E Project · President's Budget PB2027

MH-60 Service Life Modernization

FY2027 Request
$32.5M
◆ New start in FY2027
HitchAI read

Project 1709 — MH-60 Service Life Modernization requests $32.5M in FY2027, 37% of the $88.9M requested for program element 0604216N — a new start, with no prior-year and no current-year money. 1 R-2A activity decomposes the request, 1 new this cycle. NAWCAD is the largest named R-3 performer at $0.4M, 1.1% of the project's FY2027 R-3 total.

New start

This project requests $32.5M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

FY2027 Request
$32.5M
No FY2026 funding
FY2026 Enacted
$0.0M
No FY2025 funding
FY2025 Actual
$0.0M
Prior year
Project detail

What project 1709 buys

Under SLM, the MH-60 program will develop an open agile architecture that resolves multiple obsolescence issues within the flight critical avionics, and mission systems that can rapidly respond to emerging threats and fleet requirements ensuring the MH-60 continues to be a relevant, supportable, and cost-effective platform. FY 2027 budget request funds the following: 1. Initiate development of acquisition documentation for TALON Middle-Tier-of-Acquisition prototypes 2. Refine the TALON System Model for both the Flight Critical Avionics Segment (FCAS) and the Mission Systems and Weapon Segment (MSWS) 3. Award initial contract for the preliminary design of the FCAS and Digital Backbone (DBB) 4. Identify and develop test infrastructure and support building initial test development requirements for SLM efforts 5. FY 2027 funds lay the groundwork for multiple contract awards (including OTAs) in FY 2028

R-3 lines of work
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
Funding trajectory

Project 1709 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

5010015000.0FY25ACTUAL0.0FY26ENACTED32.5FY27REQUEST172.2FY28140.7FY29162.5FY30117.0FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual0.0
FY2026Enacted0.0
FY2027Request32.5
FY2028Outyear172.2
FY2029Outyear140.7
FY2030Outyear162.5
FY2031Outyear117.0
Inside the project

1 accomplishment / planned program

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Coverage is partial across the corpus, so count activities, never total them.

Service Life ModernizationNEW
FY2025 actual$0.0M
FY2026 enacted$0.0M
FY2027 request$32.5M

FY2027 planned work Develop the preliminary design of the TALON FCAS and DBB segments through award of initial contract. Establish government support for SLM requirements. Initiate development of acquisition documentation for TALON MTA efforts. Identify and develop test infrastructure and support building initial test development requirements for SLM efforts.

FY2026 to FY2027 change FY 2027 commences TALON development efforts under PU 1709.

Who's building it

Named performers on project 1709

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

NAWCAD
$0.4M · 1.1%