RDT&E Project · President's Budget PB2027

Unified Network Technology Trans & Integ (UNTTI)

FY2027 Request
▼ 100% vs FY2026
HitchAI read

Project DD1 — Unified Network Technology Trans & Integ (UNTTI) requests — in FY2027, 0.0% of the $42.6M requested for program element 0604818A, down 100% on FY2026. 6 R-2A activities decompose the request.

FY2027 Request
$0.0M
▼ 100% vs FY2026
FY2026 Enacted
$14.5M
▲ 14% vs FY2025
FY2025 Actual
$12.7M
Prior year
Project detail

What project DD1 buys

In FY 2027, this effort was transferred to PE 0605330A (C2 Transport) / Project C2A (Satellite and Network Modernization). Project DD1, Unified Network Technology Transition and Integration (UNTTI) supports the Army's Command Control (C2) Transport strategy. UNTTI is an RDT&E initiative enabling transport agnostic, high-capacity and resilient tactical communications for expeditionary operations. UNTTI efforts support system/subsystem development and demonstration, aimed at integration, maturation, evaluation, and testing to demonstrate systems against requirements. TEM Projects, Line of Sight Modernization, SATCOM Modernization, Transport Modernization, Secure Cellular, and System of Systems (SoS) Training. These technologies support new and improved communications capabilities with reduced Size, Weight, and Power (SWAP), while increasing throughput, providing network resiliency and Low Probability of Intercept/Low Probability of Detection (LPI/LPD) capabilities. The Program Executive Office Command, Control, Communications and Network (PEO C3N) is responsible for prioritizing, programming, managing and executing the projects detailed below and ensuring these funds are available to support the Army modernization priorities. The Command and Control Cross Functional Team (C2-CFT), Command, Control, Communications, Computers, Cyber, Intelligence, Surveillance and Reconnaissance (C5ISR) Center, Army Capability Network (ACM) Networks and Services (N&S) support the prioritization of technology demonstrations, focused evaluations, and expert analyses to inform future requirements, mature technologies, and deliver new capabilities. These projects inform technology integration, support user assessments, and transition to programs if appropriate. UNTTI procures, modifies, integrates, and tests system prototypes to demonstrate enhanced capabilities in accordance with Army modernization priorities. UNTTI supports developing technical, logistics, training, and other acquisition documentation to assist with the transition, insertion, and integration of efforts across PM Tactical Network and enables the transition of developing and new technologies to support Next Generation Command and Control (NGC2). In addition, UNTTI resources validation and test efforts which improves the reliability, maintainability, and supportability of Tactical Network equipped units.

R-3 lines of work
  • Management Services
  • Product Development
  • Test and Evaluation
Funding trajectory

Project DD1 funding, FY2025–FY2026

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

012.7FY25ACTUAL14.5FY26ENACTED
Actual Enacted
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual12.7
FY2026Enacted14.5
Inside the project

6 accomplishments / planned programs

The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Coverage is partial across the corpus, so count activities, never total them.

Systems Engineering and Program Management▼ 100%
FY2025 actual$1.3M
FY2026 enacted$1.4M
FY2027 request

FY2026 to FY2027 change In FY 2027, this effort was transferred to PE 0605330A (C2 Transport) / Project C2A (Satellite and Network Modernization).

FY2026 plans — current year Funds matrix and contractor personnel labor and travel requirements in support of multiple planned Soldier Touch Points and other demonstration/exercise/training events. Includes program oversight, systems engineering and technical control, risk management, documentation, and fielding support for UNTTI efforts.

FY2025 accomplishments Funds matrix and contractor personnel labor and travel requirements in support of multiple planned Soldier Touch Points and other demonstration/exercise/training events. Includes program oversight, systems engineering and technical control, risk management, documentation, and fielding support for UNTTI efforts.

TEM Projects - Pathway Diversity
FY2025 actual$1.2M
FY2026 enacted
FY2027 request

FY2025 accomplishments Funds improve the usability, security, and performance aspects of the software based on operational feedback. Funds software modification, software licenses, evaluation of hardware integration options, and supports initial demonstrations of capability to select Army Units to understand integration and performance at scale. Funds development of sustainment strategy and completes development, testing, and integration of this project.

Secure Cellular▼ 100%
FY2025 actual
FY2026 enacted$4.9M
FY2027 request

FY2026 to FY2027 change Effort completed.

FY2026 plans — current year Funds will procure, modify and harden advanced cellular equipment that will provide cellular service to enable next generation command and control applications to keep warfighters updated and connected.

TEM Projects - Gateway Automation▼ 100%
FY2025 actual
FY2026 enacted$2.7M
FY2027 request

FY2026 to FY2027 change Effort completed.

FY2026 plans — current year Funds will improve capabilities based on prototype feedback and soldier touchpoints, integrate at RHN to understand performance at scale, and develop the appropriate acquisition documentation necessary for soldier training and sustainment.

Transport Modernization▼ 100%
FY2025 actual$10.0M
FY2026 enacted$5.3M
FY2027 request

FY2026 to FY2027 change In FY 2027, this effort was transferred to PE 0605330A (C2 Transport) / Project C2A (Satellite and Network Modernization). Transport Modernization efforts are realigned to Transport Modernization Terminals and Transport Modernization - Network Efficiency to better align funds with Army's tactical transport/network priorities and provide more transparency into planned efforts within Transport Modernization.

FY2026 plans — current year Funds will be used for prototype procurement and modification of an emerging technology in transport modernization, along with integration and testing of modernized solutions. Funds evaluation of hardware form factor variants and supports integration and testing with various Army platforms.

FY2025 accomplishments Funds will be used for prototype procurement and modification of an emerging technology in transport modernization, along with integration and testing of modernized baseband solutions. Funds evaluation of hardware form factor variants and supports integration and testing with various Army platforms. Funds integration, testing, and evaluation of emerging technologies in transport modernization in support of NGC2.

System of System (SoS) Training▼ 100%
FY2025 actual$0.3M
FY2026 enacted$0.3M
FY2027 request

FY2026 to FY2027 change In FY 2027, this effort was transferred to PE 0605330A (C2 Transport) / Project C2A (Satellite and Network Modernization).

FY2026 plans — current year Funds will be used to develop System of Systems (SoS) training materials for units that have multiple integrated systems from across the PM Tactical Network portfolio.

FY2025 accomplishments Funds will be used to develop System of Systems (SoS) training materials for units that have multiple integrated systems from across the PM Tactical Network portfolio.