R-2A Activity · President's Budget PB2027

Test and Evaluation

FY2027 Request
$34.9M
◆ New start in FY2027
HitchAI read

This activity requests $34.9M in FY2027, 5.0% of project DP3 — a new start with no prior-year and no current-year money. The R-2A exhibit describes it across FY2027, including what the FY2027 money is planned to buy.

New start

This activity requests $34.9M in FY2027 with no prior-year and no current-year funding. There is no incumbent line to compare it with — it did not exist before this President's Budget.

FY2027 Request
$34.9M
President's Budget
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project DP3 of PE 0604854A. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

FY27 funding will execute the required testing to enable Soldier experimentation events in FY28. Key events include formally characterizing system performance, developmental and live fire testing, verifying U.S. ammunition compatibility, validating fire control and network interoperability, and initiating the system safety certification for both the MTC and RSV. Supports test site personnel, facilities, developmental and live fire testing, operational scenarios, safety release testing, and ammunition required to conduct system evaluations, including U.S. ammo compatibility and integration to the U.S. fires network, as well as soldier experimentation.

FY2026 to FY2027 change

This element was realigned from program 0203743A, project FF9. The FY 2027 funding increase is due to a shift in the Acquisition Strategy. The program conducts developmental and safety testing in preparation for a Soldier Experimentation event in FY 2028.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25034.9FY27REQUEST
Request
Fiscal YearEstimate TypeAmount ($M)
FY2027Request34.9

This activity is 5.0% of project DP3's FY2027 request and 4.9% of PE 0604854A's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

3 activities in project DP3

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Product Development$646.4M NEW
Test and Evaluation — this activity$34.9M NEW
Program Management$15.3M NEW
Source
FY2027 Department of the Army RDT&E Budget Justification · Exhibit R-2A · PE 0604854A, project DP3 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0604854A/DP3/a2.md · MCP mcp.hitchintel.combudget_get_activity