R-2A Activity · President's Budget PB2027

Technical/Program Management and Support

FY2027 Request
$11.4M
▲ 111% vs FY2026
HitchAI read

This activity requests $11.4M in FY2027, 14% of project A97, up 111% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$11.4M
▲ 111% vs FY2026
FY2026 Enacted
$5.4M
In law
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project A97 of PE 0605275A. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

The Army will continue to fund engineering and technical assistance after program initiation. The Army will fund program management support, core information technology requirements, Government matrix technical expertise, and shared services requirements via various Government contracts.

FY2026 to FY2027 change

Fiscal Year (FY) 2027 funding will support increase to Technical/Program Management and Support as all three LOEs increase in activity. The increase in contract actions, test events, and prototype issue and evaluation will necessitate increased program office oversight.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

The Army plans to establish the CSR Product Office, focusing on staffing and establishing technical assistance contracts to ensure program success. The Army will fund initial engineering and technical assistance at program initiation. The Army will fund a Federally Funded Research and Development (FFRDC) agency for development and integration technical expertise. The Army will also fund program management support, core information technology requirements, Government matrix technical expertise, and shared services requirements via various Government contracts.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

05.4FY26ENACTED11.4FY27REQUEST
Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2026Enacted5.4
FY2027Request11.4

This activity is 14% of project A97's FY2027 request and 11% of PE 0605275A's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

5 activities in project A97

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

LOE 3 Prototype Development$37.5M ▲ 400%
LOE 1 Prototype Development$22.0M ▲ 33%
Technical/Program Management and Support — this activity$11.4M ▲ 111%
LOE 2 Prototype Development$5.8M ▲ 130%
Prototype Demonstration/Test$4.5M ▲ 80%
Source
FY2027 Department of the Army RDT&E Budget Justification · Exhibit R-2A · PE 0605275A, project A97 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.