What the FY2027 request buys
Verbatim from the R-2A exhibit for project A5C of PE 0605345A. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.
Provides Systems Engineering and Program Management support for the development and integration of future UAS systems.
FY 2027 funding increase supports the start of the Future Group 4+ UAS S/VTOL program as well as new iterations of BDE assets. This funding was realigned from PE 0604113A - Future Tactical Unmanned Aircraft System (FTUAS), Project EX8 - Future Unmanned Aircraft System (FUAS).
FY2026: the year under way
Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.
Provides Systems Engineering and Program Management support for the development and integration of future UAS systems.
Three years, and no five-year plan
An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2026 | Enacted | 0.3 |
| FY2027 | Request | 13.9 |
This activity is 2.9% of project A5C's FY2027 request and 1.7% of PE 0605345A's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.
3 activities in project A5C
Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.