What project 6606MR buys
This project's mission is not performed under this program.
Project 6606MR funding, FY2025–FY2031
Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.
| Fiscal Year | Estimate Type | Amount ($M) |
|---|---|---|
| FY2025 | Actual | 0.0 |
| FY2026 | Enacted | 0.0 |
| FY2027 | Request | 211.4 |
| FY2028 | Outyear | 287.8 |
| FY2029 | Outyear | 248.3 |
| FY2030 | Outyear | 104.6 |
| FY2031 | Outyear | 97.1 |
1 accomplishment / planned program
The R-2A exhibit — the only level of the budget that describes work that has not happened yet. Activities carry the prior, current and budget year only, no five-year plan. Coverage is partial across the corpus, so count activities, never total them.
FY2027 planned work FY 2027 Budget Year Plans include beginning test capability development for: Advanced Turbine Engines, Aerodynamic and Weapon Integration, and Advanced Landing Gear.
FY2026 to FY2027 change FY 2026 (Current Year) to FY 2027 (Budget Year) increase of 211.370 million for Strike Assets.
FY2026 plans — current year FY 2026 Current Year does not have any funding.