R-2A Activity · President's Budget PB2027

Foundational Logistics Information Technology Enterprise System (FLITES)

Activity a4·Project 675207 — Logistics IT System Modernization·PE 0708610F·U.S. Air Force
FY2027 Request
$14.6M
▼ 19% vs FY2026
HitchAI read

This activity requests $14.6M in FY2027, 68% of project 675207, down 19% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$14.6M
▼ 19% vs FY2026
FY2026 Enacted
$18.1M
▲ 129% vs FY2025
FY2025 Actual
$7.9M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 675207 of PE 0708610F. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

- Will continue business process transformation, compliance, enhancements, and integration with other systems using agile incremental releases. - Will continue configuration of commercial platform to provide foundational logistics capability. - Will conduct recurring cyber security and system performance testing concurrent with configuration. - Will continue and complete development of Item APIs. - Will continue and complete development of cataloging inputs and interfaces with DLMS. - Will continue and complete efforts to meet ICAM and FIAR compliance. - Will begin development of the interface with Theater Integrated Combat Munitions System (TICMS). - Will begin development of the interface with Enterprise Supply Chain Analysis, Planning and Execution (ESCAPE) system. - Will begin development of capabilities to subsume the D200 E/F/H system suite to manage requirements and supply positions for weapon system and aircraft spare parts.

FY2026 to FY2027 change

- Funding decrease due to decrease in total development efforts needed to meet the requirements for FLITES in FY27.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

- Continue business process transformation, compliance, enhancements, and integration with other systems using agile incremental releases. - Continue configuration of commercial platform to provide foundational logistics capability. - Conduct recurring cyber security and system performance testing concurrent with configuration. - Finalize and deploy Foundational Logistics Information Technology Enterprise System (FLITES) 1.2 with provisioning capabilities fully replacing unsupportable 50 year old item management system. - Continue and complete Federal Logistics Information System (FLIS) efforts for data transformation, increased cyber security, and Defense Logistics Management Standards (DLMS) and Financial Improvement and Audit Readiness (FIAR) compliance. - Begin development of Item Application Programming Interfaces (APIs). - Begin development of cataloging inputs and interfaces with DLMS. - Continue efforts to meet Identity, Credential, and Access Management (ICAM) and FIAR compliance. - FLITES will replace Item Management Control System (IMCS) capabilities in FY 2026.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

07.9FY25ACTUAL18.1FY26ENACTED14.6FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual7.9
FY2026Enacted18.1
FY2027Request14.6

This activity is 68% of project 675207's FY2027 request and 68% of PE 0708610F's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

6 activities in project 675207

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the program-element page.

Foundational Logistics Information Technology Enterprise System (FLITES) — this activity$14.6M ▼ 19%
Integrated Logistics System-Supply (ILS-S)$2.9M NEW
Enterprise Logistics Management System (ELMS)$2.9M NEW
Field Maintenance (Field Mx)$1.0M ▲ 862%
Enhanced Technical Information Management System (ETIMS)$0.0M
Supply Capability Initiative (SCI)$0.0M ▼ 100%
Source
FY2027 Department of the Air Force RDT&E Budget Justification · Exhibit R-2A · PE 0708610F, project 675207 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access
Markdown twin /programs/0708610F/675207/a4.md · MCP mcp.hitchintel.combudget_get_activity