R-2A Activity · President's Budget PB2027

Combatant Craft Medium (CCM), Program Number 818

Activity a0·Project S1684 — Surface Craft·PE 1160483BB·Defense-Wide
FY2027 Request
$43.5M
◆ Restart — nothing in FY2026
HitchAI read

This activity requests $43.5M in FY2027, 67% of project S1684 — a restart, funded in FY2025 and zeroed in FY2026. The R-2A exhibit describes it across FY2025–FY2027, including what the FY2027 money is planned to buy.

Restart

This activity was funded in FY2025 ($18.2M), zeroed in FY2026, and requests $43.5M again in FY2027. A restart has an incumbent and a new start does not; with a zero current year there is no percentage to quote, which is why it appears in no growth ranking.

FY2027 Request
$43.5M
No FY2026 funding
FY2026 Enacted
$0.0M
▼ 100% vs FY2025
FY2025 Actual
$18.2M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project S1684 of PE 1160483BB. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Continues the incremental design, development, and production of the CCM Mk2 EDM, to include Government engineering services, test agency support, and industry subject matter expertise.

FY2026 to FY2027 change

Increase of $43.471 million supports the continued survivability test and evaluation for CCM Mk1 sensors and antennas and the continued development and production of the CCM Mk2 Engineering Development Model, to include Government engineering services, test agency support, and industry subject matter expertise.

Before the request year

FY2025–FY2026: what came before

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

Initiate the incremental development of the CCM Mk2 Engineering Development Model (EDM). Note: FY 2026 President's Budget included $0.00 million in discretionary funding and $28.196 million in mandatory funding for CCM.

FY2025 accomplishments

Begin Engineering and Manufacturing Development (EMD) phase for the CCM Mk2.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

25018.2FY25ACTUAL0.0FY26ENACTED43.5FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual18.2
FY2026Enacted0.0
FY2027Request43.5

This activity is 67% of project S1684's FY2027 request and 12% of PE 1160483BB's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

8 activities in project S1684

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Combatant Craft Medium (CCM), Program Number 818 — this activity$43.5M RESTART
Combatant Craft Mission Equipment (CCME)$17.8M RESTART
Combatant Craft Assault (CCA), Program Number 820$1.8M RESTART
Combatant Craft Heavy (CCH), Program Number 819$1.0M RESTART
Special Operations Craft Riverine (SOCR), Program Number 821$0.6M RESTART
Maritime Precision Engagement (MPE), Program Number 671$0.0M
Combatant Craft Forward Looking Infrared (CCFLIR) Program No. 822$0.0M
Classified Program$0.0M
Source
FY2027 Office of the Secretary of Defense RDT&E Budget Justification · Exhibit R-2A · PE 1160483BB, project S1684 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.
Machine access