LTRS Range Technology Integration

Activity a2·Project 674137 — Launch and Test Range System (LTRS) Modernization·PE 1203182SF·U.S. Space Force
FY2027 Request
$20.8M
▼ 27% vs FY2026
HitchAI read

This activity requests $20.8M in FY2027, 37% of project 674137, down 27% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$20.8M
▼ 27% vs FY2026
FY2026 Enacted
$28.4M
▲ 244% vs FY2025
FY2025 Actual
$8.2M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 674137 of PE 1203182SF. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Maintaining capability while modernizing and accelerating engineering innovation to the Ranges and Spaceports. Adopt modern systems, infrastructure, platforms, and processes to increasingly rely on Cloud-based infrastructure with Cloud-native data governance regimes to sustain future operational data needs. Facilitating the shift of commercial launch customers to AFSS systems and the continued shift for government launch customers away from the FTS system towards AFSS configuration. Continue efforts to analyze, engineer, and prototype SOTF envisioned agility and resiliency through a Digital Transformation strategy while upgrading rapid data delivery for decision-support in an increasingly contested operational environment. Transforming Range resiliency and launch customer responsiveness with data and AI-enabled predictive modeling for real-time decision support. Development teams and digital support services will facilitate prototypes and data-driven test applications to accelerate delivery of capabilities to range users. Progress against goals such as agile Range situational awareness and LTRS equipment automation to facilitate rapid range reconfiguration and continued expansion of capability to conduct simultaneous launch operations. Harness proven LTRS CI/CD pipeline and established Dev/Sec/Ops approach for deploying LTRS system applications and transitioning legacy data transport for accelerated analysis and mission support. Implement system resiliency and situational awareness necessary to operate in a contested space and cyber domains, while improving operational efficacy through customer-responsive iteration, testing, prototyping, and releases throughout increased operational use. Activities include, but are not limited to, program office strategy advisement on advanced technology adoption, studies, technical analyses, experimentation, prototyping, etc. Decision-support delivered to senior leaders for progress against SOTF objectives.

FY2026 to FY2027 change

A minor decrease in funds from FY 2026 to FY 2027 still enables the integration of sensor edge data and range system data to meet current technology demands via a hybrid cloud environment with AI-enabled data handling capabilities, ensuring secure data handling and transmission for spacelift mission support.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

Provide engineering and integration support to both sustainment and development projects aimed at increasing spaceport capacity, responsiveness and agility including the Delta-V SWP, data transport and handling improvements, and sensor edge modernization. Adopt modern systems, infrastructure, platforms, and processes to increasingly rely on Cloud-based infrastructure with Cloud-native data governance regimes to sustain future operational data needs. Facilitating the shift of commercial launch customers to AFSS systems and the continued shift for government launch customers away from the FTS system towards AFSS configuration. Continue efforts to analyze, engineer, and prototype SOTF envisioned agility and resiliency through a Digital Transformation strategy while upgrading rapid data delivery for decision-support in an increasingly contested operational environment. Transforming Range resiliency and launch customer responsiveness with data and predictive modeling for real-time decision support. Development teams and digital support services will facilitate prototypes and data-driven test applications to accelerate delivery of capabilities to range users. Progress against goals such as agile Range situational awareness and LTRS equipment automation to facilitate rapid range reconfiguration and continued expansion of capability to conduct simultaneous launch operations. Harness proven Delta-V SWP Dev/Sec/Ops approach for deploying LTRS system applications and transitioning legacy data transport for accelerated analysis and mission support. Implement system resiliency and situational awareness necessary to operate in a contested space and cyber domain, while improving operational efficacy through testing and prototyping throughout increased operational use. Activities include, but are not limited to, project support, program office strategy advisement on advanced technology adoption, studies, technical analyses, experimentation, prototyping, etc. Decision-support delivered to senior leaders for progress against SOTF objectives.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

2508.2FY25ACTUAL28.4FY26ENACTED20.8FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual8.2
FY2026Enacted28.4
FY2027Request20.8

This activity is 37% of project 674137's FY2027 request and 37% of PE 1203182SF's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

3 activities in project 674137

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the program-element page.

Delta-V$36.0M ▲ 39%
LTRS Range Technology Integration — this activity$20.8M ▼ 27%
Enterprise Systems Engineering and Integration to Support Government-Controlled Baseline$0.0M
Source
FY2027 Department of the Air Force RDT&E Budget Justification · Exhibit R-2A · PE 1203182SF, project 674137 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.