R-2A Activity · President's Budget PB2027

Undergraduate Jet Training System (UJTS)

FY2027 Request
$69.7M
▲ 1686% vs FY2026
HitchAI read

This activity requests $69.7M in FY2027, 87% of project 3367, up 1686% on FY2026. The R-2A exhibit describes it across FY2026–FY2027, including what the FY2027 money is planned to buy.

FY2027 Request
$69.7M
▲ 1686% vs FY2026
FY2026 Enacted
$3.9M
▼ 44% vs FY2025
FY2025 Actual
$6.9M
Prior year
Planned work

What the FY2027 request buys

Verbatim from the R-2A exhibit for project 3367 of PE 0603208N. This is the budget justification's own description of work that has not happened yet — the one thing no other level of the budget carries.

FY2027 planned work

Continue Source Selection activities. Award the UJTS Engineering and Manufacturing Development contract. Secure Milestone B approval from the Milestone Decision Authority.

FY2026 to FY2027 change

Increase of $65.769M from FY2026 to FY2027 due to evolution of UJTS program from source selection activities done solely by Government labor to contract award of the engineering and manufacturing design phase of the UJTS program.

Before the request year

FY2026: the year under way

Prior-year accomplishments and current-year plans from the same exhibit. Context for the FY2027 plan, not a series — an activity partitions its project exactly in the request year, but can under-cover it in earlier years.

FY2026 plans — current year

Continuing efforts to develop Requirements Documents, Cybersecurity Strategy, Test and Evaluation Master Plan (TEMP), Acquisition Plan/Strategy, Funding Profile, Source Selection Plan, Risk Management Plan, Life Cycle Cost, and related documents required for the solicitation and commencement of source selection. Inform industry of the scope of the UJTS program effort to facilitate the program Request for Proposals and eventual program competition. Continue government support labor to facilitate all program efforts. Secure RFP release approval from the Milestone Decision Authority.

Money

Three years, and no five-year plan

An R-2A activity publishes the prior year, the current year and the budget year. The FYDP outyears exist at project and program-element level and are deliberately absent here rather than inferred. Estimate types are colored and never summed into one figure.

255006.9FY25ACTUAL3.9FY26ENACTED69.7FY27REQUEST
Actual Enacted Request
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual6.9
FY2026Enacted3.9
FY2027Request69.7

This activity is 87% of project 3367's FY2027 request and 86% of PE 0603208N's. In the request year the activities under a project sum to it exactly; in the current year they under-cover it in about 9% of cases, so an activity's delta can legitimately exceed its parent's and the two must not be compared row to row.

Where this sits

3 activities in project 3367

Every R-2A line of this project, largest FY2027 request first. Linked where the activity has enough of its own narrative to carry a page; the rest are shown in full on the project page.

Undergraduate Jet Training System (UJTS) — this activity$69.7M ▲ 1686%
T-6B Avionics Modernization$7.4M ▼ 2%
Training System Improvements$2.8M ▼ 4%
Source
FY2027 Department of the Navy RDT&E Budget Justification · Exhibit R-2A · PE 0603208N, project 3367 (President's Budget PB2027). Congressional marks are recorded on the program element, never on an activity.