U.S. Navy requests $1.0M in FY2027, before stepping down 49% across the five-year plan. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators funded it in full. Sikorsky leads the industry work.

FY2027 Request
$1.0M
▼ 1.1% vs FY2026
FY2026 Enacted
$1.0M
No FY2025 funding
FY2025 Actual
$0.0M
Prior year

For fiscal year 2027, the U.S. Navy is requesting $1.0M for Other Helicopter Development under RDT&E program element 0604212N, down 1.1% from FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

00.0FY25ACTUAL1.0FY26ENACTED1.0FY27REQUEST1.0FY281.0FY290.5FY300.5FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual0.0
FY2026Enacted1.0
FY2027Request1.0
FY2028Outyear1.0
FY2029Outyear1.0
FY2030Outyear0.5
FY2031Outyear0.5
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 5 — System Development & Demonstration.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Complete
Prototyping
BA 4
Current
Development & Fielding
BA 5–7
Inside the program element

1 project rolls up into PE 0604212N

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves -1% overall, which can hide much larger swings below.

Project 1109

CH/MH-53

$1.0MFY2027 request ▼ 1%
FY2025 actual$0.0M
FY2026 enacted$1.0M
FY2027 request$1.0M
Product DevelopmentSupportTest and EvaluationManagement Services

The H-53 helicopter is the premier heavy lift helicopter for the Marine Corps and the only operational airborne mine sweeping platform for the Navy. H-53 efforts will continue to develop and qualify components, prior to production and approval decisions, in order to replace obsolete system components. Emphasis will be placed on safety/readiness/supportability improvement modifications that will sustain the H-53 aircraft until the transition of the H-53K is complete. These efforts combined, will significantly improve the readiness of the H-53 fleet while reducing long term operational and supportability costs. Survivability efforts to address improved situational awareness to pilots. Modeling and simulation will be used to the maximum practical extent throughout this effort. Manned Flight Simulator will be utilized to develop, install and test interim modifications, while maintaining the original basic system footprint and functionality. As a part of this effort, a complete Electro Magnetic Vulnerability assessment will be required for the affected and/or modified systems.

Accomplishments / planned programs (R-2A) — prior, current and budget year only
H-53 Survivability▼ 1%
FY2025 actual$0.0M
FY2026 enacted$1.0M
FY2027 request$1.0M

FY2027 planned work Continue to perform trade studies, risk reduction, design, development, model, integration and test activities for H-53 safety and survivability to include increased situational awareness.

FY2026 to FY2027 change Decrease of $.011M from FY 2026 to FY 2027 due to decreased survivability analysis requirements.

FY2026 plans — current year Perform trade studies, risk reduction, design, development, model, integration and test activities for H-53 safety and survivability to include increased situational awareness.

Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$1.0M
House NDAA (HASC)HASC
$1.0M full · +$0
Senate NDAA (SASC)SASC
$1.0M full · +$0
House Approps (HAC-D)HAC_D
$1.0M full · +$0
unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

Sikorsky
$1.0M · 100%
Systems Engineering Contract · IDDQ
Where FY2027 funding flowsShare$M
Industry primes100%1.0
FY2027 request100%1.0
See Sikorsky's full federal contract ledger members
Program detail

Mission & acquisition strategy

The H-53 helicopter is the premier heavy lift helicopter for the Marine Corps and the only operational airborne mine sweeping platform for the Navy. H-53 efforts will continue to develop and qualify components, prior to production and approval decisions, in order to replace obsolete system components. Emphasis will be placed on safety/readiness/supportability improvement modifications that will sustain the H-53 aircraft until the transition of the H-53K is complete. These efforts combined, will significantly improve the readiness of the H-53 fleet while reducing long term operational and supportability costs. Survivability efforts to address improved situational awareness to pilots.

This is a non-ACAT program.

Project 1109 — CH/MH-53
  • Product Development
  • Support
  • Test and Evaluation
  • Management Services
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?How is the FY2027 request split between industry and government performers?In plain terms, what is this program element for and how is it being acquired?

This page carries the budget justification and the NDAA marks — nothing else. For what Sikorsky has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Navy RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0604212N (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Other Helicopter Development (PE 0604212N)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0604212N
Machine access
Markdown twin /programs/0604212N.md · MCP mcp.hitchintel.combudget_get_program_element, budget_get_cong_marks