RDT&E Program Element · President's Budget PB2027

Standards Development

PE 0604215N·U.S. Navy·Approp. 1319 — RDT&E·BA5 — System Development & Demonstration
FY2027 Request
$4.4M
Navy · RDT&E
HitchAI read

U.S. Navy requests $4.4M in FY2027, sustained across the five-year plan. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators funded it in full.

FY2027 Request
$4.4M
▼ 3.1% vs FY2026
FY2026 Enacted
$4.5M
▼ 7.7% vs FY2025
FY2025 Actual
$4.9M
Prior year

For fiscal year 2027, the U.S. Navy is requesting $4.4M for Standards Development under RDT&E program element 0604215N, down 3.1% from FY2026.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

04.9FY25ACTUAL4.5FY26ENACTED4.4FY27REQUEST3.7FY284.6FY293.5FY304.7FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual4.9
FY2026Enacted4.5
FY2027Request4.4
FY2028Outyear3.7
FY2029Outyear4.6
FY2030Outyear3.5
FY2031Outyear4.7
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 5 — System Development & Demonstration.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Complete
Prototyping
BA 4
Current
Development & Fielding
BA 5–7
Inside the program element

1 project rolls up into PE 0604215N

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves -3% overall, which can hide much larger swings below.

Project 1857

Calibration Standards

$4.4MFY2027 request ▼ 3%
FY2025 actual$4.9M
FY2026 enacted$4.5M
FY2027 request$4.4M
Product DevelopmentManagement Services

Navy-wide program which addresses Metrology related RDT&E issues for navy weapon systems, shipboard platforms, Naval Air, and Fleet Ground Marines. It supports development of calibration standards (equipment, procedures and technical data) required to resolve METCAL related safety, obsolescence, new and emerging technology support and cost reduction issues. It funds Navy unique and lead service responsibilities in DoW and Joint Services Metrology Research Programs to develop calibration solutions. The line supports development of measurement requirements to verify performance of all test systems used to validate the operation of Navy Weapon Systems with calibration standards traceable to the National Institute of Standards and Technology to calibrate, sustain and ensure performance accuracy. This program also provides benefits and efficiencies in a joint collaborative environment within the Tri-Services. Projects are identified and defined so that they will meet the universal requirement. Development efforts are integrated in order to achieve the common capabilities required at minimum cost. This is also a regular and common business practice within the Navy Metrology Community where R&D efforts are communicated and integrated into the multiple testing and Monitoring Systems. This is done in support of Program Managers, Sponsors, and Principle Executive officers. As a result, common requirements are established, duplication of efforts are eliminated, and best value, high quality METCAL products are produced for the Navy.

Accomplishments / planned programs (R-2A) — prior, current and budget year only
Calibration Standards▼ 3%
FY2025 actual$4.9M
FY2026 enacted$4.5M
FY2027 request$4.4M

FY2027 planned work ($1.278) Continue development of (1) Fiber Optic Time-of-Flight System Upgrade to support shipboard Readiness of Weapon System communication to Missile Launch Systems. Capability supports main data communications on the U.S. Navy's surface ships and submarines. Continue development of (1) 3D Printer Measurement Standards and Processes for Automated Parts Qualification in support of operational readiness whose performance is vital to the production of on-demand replacement parts. This effort provides timely and efficient replacement prototyping of manufactured parts with required metrological support for AM 3D printing providing a higher quality of AM produced parts in our depots, ships, and…

FY2026 to FY2027 change increase from FY26 to FY27 by .49 in the Calibration Standards Program will be applied to continue development of the Fiber Optic Time-of-Flight System Upgrade. This enhancement supports shipboard readiness by improving the precision and reliability of Weapon System communication pathways to Missile Launch Systems. The additional funding will specifically enable further prototyping, testing, and calibration necessary for operational integration aboard fleet platforms.

FY2026 plans — current year ($0.365) Begin development of (1) calibration standard for Physical/Mechanical Quantum-Based Measurement Standards supporting Temperature Metrology using dual TCVCO architecture. This modernization enhances operational readiness, improves weapon system performance, and reduces costs. The Navy's 140,000 temperature devices require 70,000 labor hours annually; this effort could cut that by 57%, avoiding $3.5M in costs per year. ($1.373) Continue development of (1) Electro/Optical calibration hardware standard for Fiber Optic Return Loss (multi-mode) to support weapon system communications, including missile launches and combat systems. Also continue (1) Fiber Optic Time-of-Flight System…

Congressional action

Congressional marks

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$4.4M
House NDAA (HASC)HASC
$4.4M full · +$0
Senate NDAA (SASC)SASC
$4.4M full · +$0
House Approps (HAC-D)HAC_D
$4.4M full · +$0
unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

Where FY2027 funding flowsShare$M
Government labs & warfare centers100%4.4
FY2027 request100%4.4
Program detail

Mission & acquisition strategy

Navy-wide program which addresses Metrology related RDT&E issues for navy weapon systems, shipboard platforms, Naval Air, and Fleet Ground Marines. It supports development of calibration standards (equipment, procedures and technical data) required to resolve METCAL related safety, obsolescence, new and emerging technology support and cost reduction issues. It funds Navy unique and lead service responsibilities in DoW and Joint Services Metrology Research Programs to develop calibration solutions.

Funds provide for in-service engineering initiation of metrology research and developmental efforts of unique non-commercial hardware standards in the development of six key thrust technological areas which correspond to Physical Mechanical, Electro-Optical, Analytical Metrology, Electrical/Electronic systems, Chembio Defense, Microwave/Millimeter wave. These standards will ensure measurement accuracy in advanced and emerging combat weapon systems and associated test equipment. These hardware test standards will also provide for cost effective and efficient system maintenance and calibration measurements that reduce wrong test decisions and will result in lower maintenance cost and higher system performance reliability.

Project 1857 — Calibration Standards
  • Product Development
  • Management Services
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did the FY2027 NDAA committees do to this request?How is the FY2027 request split between industry and government performers?In plain terms, what is this program element for and how is it being acquired?

This page carries the budget justification and the NDAA marks — nothing else. For what a contractor has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Navy RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0604215N (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Standards Development (PE 0604215N)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0604215N