RDT&E Program Element · President's Budget PB2027

Night Vision Systems - Eng Dev

PE 0604710A·U.S. Army·Approp. 2040 — RDT&E·BA5 — System Development & Demonstration
FY2027 Request
$418.4M
⚑ Contested — House approps cuts 1.6%
HitchAI read

U.S. Army requests $418.4M in FY2027 (down from a FY2026 peak), before stepping down 69% across the five-year plan. In the FY2027 defense authorization, the House funded it in full; the Senate funded it in full; House appropriators cut 1.6% (to $411.7M). RIVET leads the industry work.

FY2027 Request
$418.4M
▼ 9.3% vs FY2026
House approps mark
$411.7M
▼ $6.7M vs request
FY2026 Enacted
$461.3M
In law

Roll-up of 5 projects. Projects are the summable leaves — the PE total is their sum, never added to it.

For fiscal year 2027, the U.S. Army is requesting $418.4M for Night Vision Systems - Eng Dev under RDT&E program element 0604710A, down 9.3% from FY2026. In the FY2027 defense authorization, House approps moved to cut it to $411.7M.

Funding trajectory

Funding profile, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure.

1503004500134.6FY25ACTUAL461.3FY26ENACTED418.4FY27REQUEST152.5FY28136.1FY29128.4FY30129.7FY31HOUSE APPROPS
Actual Enacted Request Outyear (FYDP) House approps mark
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual134.6
FY2026Enacted461.3
FY2027Request418.4
FY2028Outyear152.5
FY2029Outyear136.1
FY2030Outyear128.4
FY2031Outyear129.7
Where it sits

Acquisition lifecycle

This program is funded in RDT&E Budget Activity 5 — System Development & Demonstration.

Complete
Research
BA 1–2
Complete
Advanced Technology
BA 3
Complete
Prototyping
BA 4
Current
Development & Fielding
BA 5–7
Inside the program element

5 projects roll up into PE 0604710A

Projects are the summable leaves — the PE total is their sum, never added to it. Program elements and projects carry the full five-year plan; activities stop at the budget year. This PE moves -9% overall, which can hide much larger swings below.

Congressional action

The request is contested

Committee marks on the FY2027 request. Adds and cuts are reconciled in conference before they become law.

RequestPresident's Budget
$418.4M
House NDAA (HASC)HASC
$418.4M full · +$0
Senate NDAA (SASC)SASC
$418.4M full · +$0
House Approps (HAC-D)HAC_D
$411.7M −$6.7M · −1.6%
▲ $6.7M chamber gap — unresolved as of 2026-07-27. These are FY2027 authorization marks (NDAA); appropriations and the conference agreement may differ.
Who's building it

Where the FY2027 request goes

Performers named in the R-3 exhibit, resolved into industry, government-lab, and unspecified shares. Budget-justification contract funding, not obligations.

RIVET
$87.1M · 21%
Soldier Borne Mission Command (SBMC) OTA · FFP
ELBIT
$60.9M · 15%
Soldier Borne Mission Command (SBMC) OTA · FFP
Where FY2027 funding flowsShare$M
Industry primes50%208.3
Government labs & warfare centers4.3%18.1
Other / unspecified46%192.1
FY2027 request100%418.4
See RIVET's full federal contract ledger members
Program detail

Mission & acquisition strategy

A portion of this funding line is directly aligned to the Army Modernization Priority in support of situational awareness for the Soldier. This program element provides night vision, surveillance, target acquisition mission planning, data visualization technologies required for United States defense forces to engage enemy forces twenty-four hours a day under conditions of degraded visibility due to darkness, adverse weather, battlefield obscurants, foliage and man-made structures.

SBMC development includes three vendors providing phased prototype deliveries of increasing maturity beginning 2QFY 2026 leading to demonstration of production representative prototypes to support a production decision by the end of FY 2027. SBMC prototypes will be evaluated throughout FY 2026 and FY 2027. SQD-A leverages lessons learned from IVAS 1.2 and delivered hardware now known as SBMC Surrogates, as a technology insertion to the base production agreement awarded in Dec 2022. The agreement was novated to Anduril Technologies in April 2025.

Project BQ6, DI5, L79, L70, L67 — Visual Augmentation System Eng Dev
  • Management Services
  • Product Development
  • Test and Evaluation
Ask Hitch

Ask this program element

Answers are generated from the figures on this page — the FY2027 justification exhibits and the marks tracked above — and nothing else is consulted. Confirm any figure against the cited exhibit before you use it externally.

H
Questions this page can answer
How does the FY2027 request compare with FY2026, and what does the five-year plan show?What did House approps do to this request, and what is still unresolved?Which project inside PE 0604710A is growing fastest, and which is shrinking?How is the FY2027 request split between industry and government performers?

This page carries the budget justification and the NDAA marks — nothing else. For what RIVET has actually been obligated, the ledger is at hitchintel.com/vendors; for live solicitations, hitchintel.com/opportunities. Both are member surfaces.

Provenance

Cite this page

Sources
FY2027 Department of the Army RDT&E Budget Justification · Exhibits R-2 / R-3 · PE 0604710A (President's Budget PB2027) — and FY2027 NDAA committee marks, as tracked 2026-07-27.
Suggested citation
HitchAI, "Night Vision Systems - Eng Dev (PE 0604710A)," federal budget intelligence, PB2027 vintage. hitchintel.com/programs/0604710A
Machine access
Markdown twin /programs/0604710A.md · MCP mcp.hitchintel.combudget_get_program_element, budget_get_cong_marks
FY2027 Request
$338.0M
▼ 19% vs FY2026
FY2026 Enacted
$418.0M
▲ 448% vs FY2025
FY2025 Actual
$76.3M
Prior year

Visual Augmentation System Eng Dev — one RDT&E project inside PE 0604710A. Congressional marks are recorded on the program element, not on a project.

Project BQ6 — Visual Augmentation System Eng Dev — requests $338.0M in FY2027, 81% of the $418.4M requested for program element 0604710A. Year over year it falls 19% against FY2026.

Funding trajectory

Project BQ6 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

100200300400076.3FY25ACTUAL418.0FY26ENACTED338.0FY27REQUEST92.1FY2893.2FY2993.2FY3094.2FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual76.3
FY2026Enacted418.0
FY2027Request338.0
FY2028Outyear92.1
FY2029Outyear93.2
FY2030Outyear93.2
FY2031Outyear94.2
Inside the project

1 accomplishment / planned program

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

FY2025 actual$76.3M
FY2026 enacted$308.0M
FY2027 request$338.0M

SBMC development includes improved system form factor and performance, and continued extensibility enhancements with SQD-A refinements. SBMC and SQD-A test and evaluation planned to assess and validate performance.

Read the FY2027 plan →
Project BQ6 — every activity in full →
Who's building it

Named performers on project BQ6

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

RIVET
$87.1M · 26%
ELBIT
$60.9M · 18%
ANDRUIL
$55.0M · 16%
Project detail

What project BQ6 buys

This project focuses on transitioning demonstrated technologies that bring improvements to provide a modular, fused digital awareness system that enhances lethality, mobility, and situational awareness for dismounted Soldiers to achieve overmatch against our current and future adversaries. Funded efforts will drive competition with multiple vendors, establish a modular open system architecture for major components, accelerate and improve thermal and low light sensor suites, terrain shared coordinate data and processing, algorithms including machine learning/artificial intelligence, human machine integration, and demonstrations in support of the next generation augmented vision, night vision, and situational awareness capabilities. Efforts will provide rapid decision making and targeting capabilities with the integration of external video and data sources such as weapon sights, air and ground platforms, unmanned air and ground assets, and other data sources enabled by edge computing devices, advanced network services, and open resilient architecture. This project includes costs for efforts associated with edge computing devices, movement of information and high-level processing, integration, and interface of products/capabilities with the Soldiers as a platform. To enable such data movement and integration, this project funds the establishment and baselining of a Squad architecture. Funding for this project aligns with the Army's Continuous Transformation priorities and National Defense Strategy. This project supports the Futures and Concepts Command (FCC) Maneuver Future Capability Directorate. The total cost of the Integrated Visual Augmentation Systems IVAS 1.2, Rapid Prototyping Middle Tier of Acquisition (RP MTA) effort is $798.10 million RDT&E from FY 2022 to FY 2027. The total cost of the Soldier Borne Mission Command (SBMC) Rapid Prototyping Middle Tier of Acquisition (RP MTA) effort is $429.8 million RDT&E from FY 2025 to FY 2027.

R-3 lines of work
  • Management Services
  • Product Development
  • Test and Evaluation
FY2027 Request
$37.7M
▲ 251% vs FY2026
FY2026 Enacted
$10.7M
▲ 6.6% vs FY2025
FY2025 Actual
$10.1M
Prior year

FALCONS — one RDT&E project inside PE 0604710A. Congressional marks are recorded on the program element, not on a project.

Project DI5 — FALCONS — requests $37.7M in FY2027, 9.0% of the $418.4M requested for program element 0604710A. Year over year it grows 251% against FY2026.

Funding trajectory

Project DI5 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

25010.1FY25ACTUAL10.7FY26ENACTED37.7FY27REQUEST26.6FY2814.8FY2910.8FY3010.9FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual10.1
FY2026Enacted10.7
FY2027Request37.7
FY2028Outyear26.6
FY2029Outyear14.8
FY2030Outyear10.8
FY2031Outyear10.9
Inside the project

1 accomplishment / planned program

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

FY2025 actual$10.1M
FY2026 enacted$10.7M
FY2027 request$37.7M

Funds in FY 2027 will finalize system design and refine modeling based on the approved performance specification. Long lead time items for prototype development will be ordered.

Read the FY2027 plan →
Project DI5 — every activity in full →
Who's building it

Named performers on project DI5

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

PM GS
$2.1M · 5.5%
Project detail

What project DI5 buys

Future Advanced Long-range Common Optical Netted-fires Sensor (FALCONS) is the next generation sensor for Reconnaissance and Fires missions to enhance lethality and survivability of Brigade Combat Teams (BCTs) in Large Scale Combat Operations (LSCO). FALCONS provides interoperability between ground platforms and dismounted personnel through a Common Operational Picture (COP) of the battlefield and interchangeable components. The enhanced capabilities of FALCONS provide the ability to detect threats at greater distances in full spectrum conflict, terrain, and weather conditions with greater image resolution to develop civil considerations. FALCONS capabilities will be part of the system of systems approach enabled by current or future data sharing networks and transport layers to transmit target quality data to effectors in operational and tactical environments maintaining overmatch in the FY 2030 and FY 2040 timeframe. FALCONS equipped systems will be part of an Army FY 2030 and FY 2040 force that is decisive in varying operations against threats in environments of national interest. The Army requires FALCONS equipped forces be operationally responsive and able to adapt and exploit patterns of operations faster than the enemy, while dominating situations and adversaries. FALCONS equipped systems are a key entity of maneuver and fires tactical forces, and provides versatility, agility, and lethality. FY 2027 funding in the amount of $37.717M will support FALCONS MTA-RP detailed design phase and procurement of "long lead" items for the Prototype development phase beginning in early FY 2028.

R-3 lines of work
  • Management Services
  • Product Development
  • Support
FY2027 Request
$20.7M
▲ 65% vs FY2026
FY2026 Enacted
$12.6M
▼ 35% vs FY2025
FY2025 Actual
$19.3M
Prior year

Joint Effects Targeting Systems (JETS) — one RDT&E project inside PE 0604710A. Congressional marks are recorded on the program element, not on a project.

Project L79 — Joint Effects Targeting Systems (JETS) — requests $20.7M in FY2027, 4.9% of the $418.4M requested for program element 0604710A. Year over year it grows 65% against FY2026.

Funding trajectory

Project L79 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

019.3FY25ACTUAL12.6FY26ENACTED20.7FY27REQUEST8.3FY289.3FY298.3FY308.4FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual19.3
FY2026Enacted12.6
FY2027Request20.7
FY2028Outyear8.3
FY2029Outyear9.3
FY2030Outyear8.3
FY2031Outyear8.4
Inside the project

2 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

JETS II Development
FY2025 actual$19.3M
FY2026 enacted
FY2027 request

In FY 2023, JETS II development contracts were awarded to two vendors; however, in FY 2025 both contracts were terminated for convenience due to their inability to meet cost and schedule requirements. The PM is exploring and assessing emerging technologies with the Fires Center of Excellence (FCoE) for a Handheld Fires System materiel…

Handheld Fires Development▲ 65%
FY2025 actual
FY2026 enacted$12.6M
FY2027 request$20.7M

FY 2027 Resources will be used to continue competitive development of Handheld Fires.

Project L79 — every activity in full →
Who's building it

Named performers on project L79

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

C5ISR (RTI)
$1.5M · 7.0%
Project detail

What project L79 buys

Project L79 supports the Joint Effects Targeting System (JETS) program and the development of Handheld Fires (HHF), which addresses the one-man, hand-held precision targeting gap identified by the Fires Center of Excellence (FCoE). JETS is a lightweight, handheld system that will provide the single dismounted observer with a common, enhanced day and night thermal capability to rapidly acquire, accurately locate, positively identify, and precisely designate targets. The Handheld Fires System will be an advanced precision targeting system incorporating improved target acquisition sensors and optics, improved targeting sensors, targeting algorithms, and a Military Code (M-Code) Global Positing System (GPS) receiver while reducing size, weight, and power requirements.

R-3 lines of work
  • Management Services
  • Product Development
  • Support
  • Test and Evaluation
FY2027 Request
$16.6M
▲ 13% vs FY2026
FY2026 Enacted
$14.7M
▲ 104% vs FY2025
FY2025 Actual
$7.2M
Prior year

Night Vision Dev Ed — one RDT&E project inside PE 0604710A. Congressional marks are recorded on the program element, not on a project.

Project L70 — Night Vision Dev Ed — requests $16.6M in FY2027, 4.0% of the $418.4M requested for program element 0604710A. Year over year it grows 13% against FY2026.

Funding trajectory

Project L70 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

07.2FY25ACTUAL14.7FY26ENACTED16.6FY27REQUEST20.0FY2813.2FY2910.5FY3010.6FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual7.2
FY2026Enacted14.7
FY2027Request16.6
FY2028Outyear20.0
FY2029Outyear13.2
FY2030Outyear10.5
FY2031Outyear10.6
Inside the project

1 accomplishment / planned program

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them. Opening lines only here — the full year-by-year narrative is on the project page.

FY2025 actual$7.2M
FY2026 enacted$14.7M
FY2027 request$16.6M

Funding supports continued digital optimization of the sensor for enhanced threat detection and recognition of the Aided Target Detection and Recognition (AiTDR) algorithms for rapid target acquisition and improved kill chain timeline. Funding also supports continued efforts to promote competition for full rate production.

Read the FY2027 plan →
Project L70 — every activity in full →
Who's building it

Named performers on project L70

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

PM TS
$1.0M · 6.0%
Project detail

What project L70 buys

The project supports the 3rd Generation Forward Looking Infrared (3GEN FLIR) B-Kit program, which incorporates the next generation of forward-looking infrared technologies. The 3GEN FLIR program provides a common 3GEN FLIR B-Kit for integration into US Army FLIR sensor systems in accordance with the approved Improved Forward Looking Infrared (I-FLIR) Capability Development Document (CDD). The common 3GEN FLIR B-Kit will integrate with XM30, FALCONS, and future platforms; with potential 3GEN FLIR component utilization opportunities for future reconnaissance and airborne applications. The 3GEN FLIR B-Kit provides Mid Wave Infrared and Long Wave Infrared digital video and the electronic interfaces required to integrate the 3GEN FLIR technology with the host platform sensor. When integrated in platform sensor packages, 3GEN FLIR technology enhances the warfighters' survivability and lethality through increased identification range performance, while enabling the detection of difficult or obscured targets and faster threat detection through automated processes. Executing Army guidance to implement advancements in digital processing and artificial intelligence has positioned 3GEN FLIR as the lead sensor to provide the Army's path forward for AI/ML capabilities for ground platforms. The 3GEN FLIR B-Kit program is key to the maintenance of the Army's FLIR industrial base.

R-3 lines of work
  • Management Services
  • Product Development
  • Support
FY2027 Request
$5.5M
▲ 4.3% vs FY2026
FY2026 Enacted
$5.2M
▼ 76% vs FY2025
FY2025 Actual
$21.7M
Prior year

Soldier Night Vision Devices — one RDT&E project inside PE 0604710A. Congressional marks are recorded on the program element, not on a project.

Project L67 — Soldier Night Vision Devices — requests $5.5M in FY2027, 1.3% of the $418.4M requested for program element 0604710A. Year over year it grows 4.3% against FY2026.

Funding trajectory

Project L67 funding, FY2025–FY2031

Prior years are actuals, the budget year is the request, and the outyears are the FYDP plan. Estimate types are colored and never summed into one figure. Projects carry the full five-year plan; the activities inside them stop at the budget year.

021.7FY25ACTUAL5.2FY26ENACTED5.5FY27REQUEST5.5FY285.6FY295.6FY305.6FY31
Actual Enacted Request Outyear (FYDP)
Fiscal YearEstimate TypeAmount ($M)
FY2025Actual21.7
FY2026Enacted5.2
FY2027Request5.5
FY2028Outyear5.5
FY2029Outyear5.6
FY2030Outyear5.6
FY2031Outyear5.6
Inside the project

2 accomplishments / planned programs

The R-2A exhibit. Activities carry the prior, current and budget year only — no five-year plan — and they are descriptive: coverage is partial and they do not always add back to the project, so count them, never total them.

Small arms fire control▲ 32%
FY2025 actual$2.8M
FY2026 enacted$2.6M
FY2027 request$3.4M

FY2027 planned work Will continue advancing prototypes through test and evaluation efforts to inform a transition to procurement. Will continue to improve target Detection, Recognition and Identification with artificial intelligence, machine learning algorithms, and advanced software solutions on prototype and production systems. Continue efforts to qualify night/day fire control devices, including improved thermal sights and integration with Fire Control, other sensors and weapon enablers on current and emerging weapons. Continue evaluating active and passive range finding and improved fire control implementations. Continue product improvements and weapon integration, to include ongoing reliability growth…

FY2026 to FY2027 change Increase in funding to support the transition to procurement efforts.

FY2026 plans — current year Will advance prototypes for test and evaluation, to include developmental testing and Soldier feedback, to inform future designs and requirements. Will continue to develop and evaluate improved target Detection, Recognition and Identification with artificial intelligence, machine learning algorithms, and advanced software solutions on prototype and production systems. Continue efforts to qualify night/day fire control devices, including improved thermal sights and integration with Fire Control, other sensors and weapon enablers. Continue evaluating active and passive range finding and improved fire control implementations. Continue product improvements and weapon integration, to include…

FY2025 accomplishments Pursue improved target Detection, Recognition and Identification with artificial intelligence, machine learning algorithms, and advanced software solutions on prototype and production systems. Begin efforts to qualify night/day fire control devices, including improved thermal sights and integration with Next Generation Fire Control, other sensors and weapon enablers. Evaluate active and passive range finding and improved fire control implementations. Continue to execute product improvements and weapon integration for the FWS Individual and FWS Sniper, to include ongoing reliability growth efforts and developmental and operational testing.

Binocular Night Observation Device (BiNOD)▼ 23%
FY2025 actual$8.9M
FY2026 enacted$2.6M
FY2027 request$2.0M

FY2027 planned work FY 2027: Follow up reliability growth testing of the BiNOD product to evaluate operational availability.

FY2026 to FY2027 change Costs decrease from FY 2026 to FY 2027 is due to BiNOD transitioning to production.

FY2026 plans — current year Continue testing of the BiNOD product in support of the Situational Awareness Strategy.

FY2025 accomplishments This program increase will fund the development of an ENVG-B rechargeable battery to improve battery performance, helmet integration, and reduced thermal signature.

Who's building it

Named performers on project L67

Performers named in the R-3 exhibit under this project. Share is of the project's whole FY2027 R-3 total — the same denominator the program-element split uses, so the two read on one scale and will not sum to 100% when unnamed or government work is in the mix. Budget-justification contract funding, not obligations.

RTI
$0.7M · 13%
Project detail

What project L67 buys

Project L67 develops, improves and miniaturizes high performance electro-optics, thermal and laser systems. It also provides for systems integration of related multi-sensor suites to enable near to long-range target acquisition and engagement as well as improved battlefield command and control in around-the-clock combat operations. It focuses on adapting demonstrated technologies that bring improvements to the dismounted Soldiers' equipment. This project develops or enhances equipment that provides the individual Soldier's day/night situational awareness and individual targeting capability and supports the Army's Situational Awareness Strategy (SAS). This project includes cost associated with efforts for the development, integration and interface of products on Soldiers head, body and weapons. Funding in this project aligns with the Army's priorities in support of the National Defense Strategy.

R-3 lines of work
  • Management Services
  • Product Development
  • Support